All Seasons Leisure Centre Improvements - Contract Award

February 12, 2026 Executive Cabinet (Other) Key decision Approved View on council website
Full council record
Content

1.     
To appoint John Turner Construction Ltd directly
through the RISE framework to carry out improvements and
decarbonisation works at All Season Leisure Centre under a JCT
Design and Build contract for £4,060,000 (excluding
VAT).

2.     
To engage Gosling Consulting for quantity surveying
and contract administration services by direct award via the Rise
Framework, at a cost of £40,000 (excluding VAT).

3.     
To authorise payment of £100,000 (excluding
VAT) to South Ribble Borough Council for the acquisition of surplus
and unused decarbonisation equipment.

4.     
To approve the contract award and authorise payment
of £113,541.75 (excluding VAT) to Electricity North West for upgrades to the electrical
supply.

5.     
To approve a £1.228 million increase to the
capital budget (excluding VAT), funded by the Salix
grant.