REG 3252 - Single Homelessness Accommodation Programme 2023-2028 (Table 1 paragraph 4e) (Part A)
December 18, 2024 Head of Planning and Housing (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve a variation of the Grant Funding Agreement for the Single Homeless Accommodation Programme due to delays at the Merrington View site, forfeiting the 5% practical completion tranche but aiming to deliver the project within budget.
Full council record
Content
The
Council was successful in its bid for funding for SHAP Single
Homeless Accommodation Programme The programme has evolved from
original submission and the consequential delays have meant that
practical completion will be unachievable for the Merrington View,
Spennymoor site by March 2025. A variation of the Grant Funding
Agreement, Capital Firm Scheme Grant Figure is now required and DCC
will forfeit the 5% practical completion tranche in line with the
Grant Funding Agreement. It is anticipated that the project can
still be delivered within the project budget by utilising
contingencies and continuing to value engineer the
scheme.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 18 Dec 2024 |