College Green - Design Services Contract and Direct Award of Structural Engineering Services
September 28, 2026 Corporate Director of Place (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Corporate Director of Place, Croydon Council, approved recommendations for a statutory consultation on changes to the Council Tax Reduction Scheme for working age claimants from 1 April 2027. The potential changes to be consulted on include reducing maximum percentage awards for specific groups, reducing the earnings disregard for disabled working claimants, and altering band caps and capital limits. The decision was made on 23 September 2026.
Full council record
Purpose
Briefly explain what the report will be about, and then set out the decision(s) required
The purpose of this report is to seek approval to:
· resume the Design Services Contract for MICA Architects, including approval for the increase in contract fee to accommodate project re-scoping, inflation, and change to the contract duration to project completion, anticipated March 2028.
· procure Structural Engineer Services for College Green Public Realm via a Direct Award to Stantec under the NHS framework.
Recommendation:
· Approve the suspension of design services delivered under the contract with MICA Architects is lifted and that the contract is extended by way of variation until 31/03/2028; with the new value as set out in Part B report.
· Approve the procurement of Structural Engineer services for College Green Public Realm via a Direct Award under the NHS framework; with the value as set out in Part B report
Decision
For the reasons set out in the report and its appendices, the Corporate Director for Place AGREED to approve:
a) that the existing contract with MICA Architects entered into in January 2020 is extended by way of variation until 31/12/2028; with the new value as set out in the Part B report.
b) the award of a contract for Structural Engineer services for College Green Public Realm (via a Direct Award under the NHS framework- Healthcare Planning, Construction Consultancy and Ancillary Services (Lot 7)) to Stantec UK Limited for the contract value set out in the Part B report.
Reasons for the decision
The continuation of both the design team (MICA Architects) and Structural Engineer (Stantec) will ensure continuation of in-depth knowledge and expertise on the project. Both fee proposals have been reviewed against the appropriateness of price and quality as reviewed with Procurement and Legal.
The recommendations are in line with Growth Zone Programme funding as approved under Mayoral Decision Report dated 09.05.25.
Alternative options considered
Other alternative options were considered and rejected for the reasons set out below:
Do Nothing:
This option is rejected as it would not support the Council’s priorities for town centre growth, regeneration and social and economic recovery at a very critical stage.
Supporting Documents
Details
| Reference | Call-ins0 |
| Outcome | Recommendations Approved |
| Decision date | 28 Sep 2026 |
| Effective from | 10 Oct 2026 |
| Lead officer | Emily Webster |
| Subject to call-in | Yes |