C229 Pow Wath Bridge U2057 – Structure Replacement

March 20, 2025 Assistant Director of Highways and Transport (Officer) Unknown View on council website
Full council record
Purpose

Permission to
procure.

Reasons for the decision

Expenditure more than £100k up to
£500k

Alternative options considered

A package of repairs to repair the concrete
and other defects were considered but they were not deemed to be
sufficient to restore the bridge to a 40T capacity. There were also
significant issues regarding the buildability of repair works that
would require dredging of the watercourse, and restricted
access/confined space construction teams.
 
Not carrying out any repairs or works was also
not deemed a feasible option as the weight limit has an impact on
road users and the structure will continue to deteriorate.

Details

OutcomeImplemented
Decision date20 Mar 2025