Following consideration, the Committee
unanimously resolved to:
(1)
Approve additional funding of £105,000 from the Capital
Receipts Reserve, to enable the Poole Road Pavilion Re-Roofing
project to proceed at an estimated cost of £255,000.
(2)
Request that internal audit look at this particular procurement to allay any Members’
concerns around it.