Hogsmill River Stepping Stones
June 30, 2026 Environment Committee (Committee) Awaiting outcome View on council websiteFull council record
Purpose
Report concerning the future of the River Hogsmill Stepping Stones
Decision
Following consideration the Committee resolved to:
(1) Agree to Option 3: Do not agree to take on the liability for the steps and stepping stones and acknowledge the EA will remove them and agree to deliver a new footbridge as an alternative safer fully accessible crossing point subject to being granted CIL funding and securing additional funding for the design and planning of a footbridge.
(2) Note the submission of the CIL application for funding the construction of a new pedestrian footbridge.
Related Meeting
Environment Committee - Tuesday, 30 June 2026 - 7.30 pm on June 30, 2026
Supporting Documents
Details
| Outcome | For Determination |