Broadcut Depot - Decarbonisation & 5 year Asset Management Plan
November 3, 2025 Executive (Other) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to deliver a Decarbonisation Scheme and five-year Asset Management Plan for the Broadcut Depot, including funding approval and delegated authority to appoint a contractor for the Decarbonisation Scheme.
Full council record
Purpose
To agree funding for a programme
of works to deliver a Decarbonisation Scheme and five-year Asset Management Plan
of essential repairs, maintenance and improvements for the Broadcut Depot.
To seek delegated authority to
appoint a contractor to deliver the Decarbonisation Scheme, following a
thorough procurement/tendered process.
The report provides details of
works to deliver a Decarbonisation Scheme for the Broadcut Depot over the next
12 months, which has been specifically designed to maximise the significant
government support available and now secured for this project.
Alongside this scheme, the
proposed Asset Management Plan ensures the provision of safe and
well-maintained premises at Broadcut Depot.
Officers have undertaken a condition survey to identify essential
repairs, maintenance and improvements required in the financial years 2025/26
to 2029/30. The information from the
condition survey has been formulated into an Asset Management Plan that
identifies the phased capital investment required over the next five years. The report provides a summary of the essential
repairs, maintenance and improvements required and an estimated budget figure
for the works.
The report seeks Executive
agreement to appoint a contractor to deliver the Depot Decarbonisation Scheme
and this will allow a start early in 2026.
Decision
RESOLVED that the Executive:
(a) agrees
the delivery of the Depot Decarbonisation Scheme at Broadcut Depot as set out
in the Executive Briefing Paper;
(b) approves
the funding of the Depot Decarbonisation Scheme works including enabling works
as detailed in the Financial Implications section of the Executive Briefing
Paper;
(c) notes
the award of government funding of £450,000 to support the depot
Decarbonisation Scheme;
(d) agrees
the delivery of the Depot 5 Year Asset Management Plan as set out in the
Executive Briefing Paper;
(e) approves
the funding of the Depot 5 Year Asset Management Plan as detailed in the
Financial Implications section of the Executive Briefing Paper; and
(f)
approves that the award of contract for the
depot Decarbonisation Scheme be delegated to the Director of Planning and
Regeneration, following consultation with the Executive Member for Policy Resources.
Related Meeting
Executive - Monday, 3rd November, 2025 6.00 pm on November 3, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 3 Nov 2025 |
| Subject to call-in | Yes |