Arnold Market Place: First Floor Enterprise Centre and Market

February 21, 2024 Leader of the Council (Cabinet member) Approved View on council website
Full council record

Purpose

The report provides a further update of the
costs of fitting out the first floor of the AMP development into an
Enterprise Centre, and requests additional budget to complete
it.

Decision

To approve a revised budget allocation of
£655,000 to support the completion of the AMP Enterprise
Centre, that is to be funded from the UKSPF Town Centre Improvement
budget in the Capital Programme.

Supporting Documents

Report to Leader - Arnold Market Place First Floor Enterprise Centre.pdf
Appendix 1 - Arnold Market First Floor Enterprise Centre - CIA.pdf
Urgent key decision notice - AMP top floor - 21.02.24.pdf

Details

OutcomeRecommendations Approved
Decision date21 Feb 2024