Procurement Pipeline Report - over £200k (2025-2026)

February 26, 2026 Executive (Other) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...approve the commencement of procurement processes for listed projects and delegate authority to the Joint Strategic Director for Finance and Resources to award contracts upon successful selection of contractors.

Full council record
Content

Decision:

1.           
Approve commencement of the procurement process for
the project(s) listed in Appendix 1 to this report; and

 

2.           
Delegate authority to the Joint Strategic Director
for Finance and Resources, having consulted with the Lead
Councillor for Finance and upon selection of a successful
contractor, to award the contract(s) as listed in Appendix
1.
 
Reason(s):
1.           
The Executive is required to approve, prior to their
commencement, all procurement activity which may require a Key
Decision for the contract award. It is good governance to seek
approval by providing Executive with a summary of all proposed
procurements that may result in a Key Decision prior to procurement
procedures formally commencing.
2.           
Planning procurement activity ensures:
·       
effective stakeholder management? 
·       
effective procurement and
sourcing? 
·       
compliance with relevant Procurement Legislation and
the Council’s own Contract Procedure Rules?? 
·       
there is consideration on how contract price is to
be managed in contract and what contract price model will be
used? 
·       
our procurement is ethical by considering factors
such as environmental and climate change impact, social value and
modern-day slavery risk.?? 
·       
how best value is to be achieved is clearly defined
including how contract management will ensure that the Council
attains best value during the life of the contract.
3.           
This report will avoid the need to submit multiple
individual requests for approval to procure and award contracts,
therefore being more agile in the approval process in relation to
procurement activity.
4.           
When a procurement activity is concluded Executive
approval for any consequent contract award which would be a Key
Decision will be sought by a separate report, unless authority is
specifically delegated to an officer.
 
Other options considered and
rejected by the Executive:
None.
Details of any conflict of
interest declared by the Leader or lead councillors and any
dispensation granted:
None.

Related Meeting

Executive - Thursday, 26 February 2026 - 6.00 pm on February 26, 2026

Supporting Documents

GBC Exec Report Procurement Pipeline 260226.pdf
Appendix 1_GBC Procurement Pipeline 260226.pdf

Details

OutcomeRecommendations approved
Decision date26 Feb 2026
Subject to call-inYes