78-80 Southway Demolition Project
February 23, 2026 Joint Assistant Director: Housing Services (Officer) Approved View on council websiteFull council record
Decision
Guildford Borough Council seeks approval to appoint a contractor to undertake urgent demolition works at 78–80 Southway following significant structural failure.
The front elevation has separated from the main structure and is currently supported by temporary a crow propping, presenting an immediate risk of collapse.
Reasons for the decision
Bearings Structural Solutions Ltd submitted the most competitive and comprehensive proposal, covering full demolition, site clearance, CDM compliance, and health and safety management.
Bearings are considered to have the appropriate technical expertise, capacity, and experience to deliver the works safely and within the required timescales.
The demolition will also support the Council’s wider regeneration objectives for the Westborough area, enabling the cleared site to be handed back to the Development team for future redevelopment and delivery of new housing stock.
Risks:
78–80 Southway has suffered significant structural failure to the extent that the front elevation has separated from the main structure and is currently being supported by a crow props. The condition of the building presents a real and imminent risk of collapse.
There have also been recent reports of unauthorised access and break-ins at the site, increasing the risk to members of the public and exposing Guildford Borough Council to significant health and safety liability.
Senior Management Team have been advised of the risks, and approval has been given by Julian Higson to proceed with demolition works as a matter of urgency to remove the immediate danger.
Alternative options considered
None
Details
| Outcome | Recommendations Approved |
| Decision date | 23 Feb 2026 |