ENTERPRISE ENGINEERING & OPTIC CENTRE CHANGE REQUEST
July 11, 2025 Awaiting outcome View on council websiteFull council record
Decision
- 1. To approve the request for change for the Enterprise, Engineering and Optics Centre project, making the following changes:
- 2. That approval be given for an additional Growth Deal investment of £446,041 to enable the project to progress to the delivery phase, subject to the funding being fully spent within the 2025-26 financial year. This investment will generate a number of additional benefits, including confirmed match funding of £250,898 from Wrexham University and the creation of six full-time equivalent jobs for the region.
Related Meeting
North Wales CJC Economic Well-being Sub-committee - Friday, 11th July, 2025 9.30 am on July 11, 2025
Details
| Decision date | 11 Jul 2025 |