ENTERPRISE ENGINEERING & OPTIC CENTRE CHANGE REQUEST

July 11, 2025 Awaiting outcome View on council website
Full council record

Decision

  1. 1.     To approve the request for change for the Enterprise, Engineering and Optics Centre project, making the following changes:
  2. 2.     That approval be given for an additional Growth Deal investment of £446,041 to enable the project to progress to the delivery phase, subject to the funding being fully spent within the 2025-26 financial year. This investment will generate a number of additional benefits, including confirmed match funding of £250,898 from Wrexham University and the creation of six full-time equivalent jobs for the region.

Details

Decision date11 Jul 2025