CHE S454 3 Year Local Implementation Plan (LIP) Delivery Plan 2025/26 - 2027/28
January 27, 2025 Approved View on council websiteFull council record
Content
RESOLVED:
1.
The 2025/26 - 2027/28 Local Implementation Plan
Delivery Plan (LIP delivery plan 2025/26 - 2027/28) and the
projects contained within, as set out in Form A (Appendix 1), were
approved to meet the requirements set out by the GLA for LIP
funding.
2.
Authority was delegated to the Assistant Director of
Streetscene, having consulted the
Cabinet Member for Climate Change, Environment and Transport and
Director of Environment and Climate Change (and subject to
certification of the Director, Financial Management, if
appropriate), to approve minor amendments to the LIP delivery plan
2025/26 - 2027/28 following TfL feedback, and prior to final
submission by the London Borough of Hackney to TfL (February
2025).
3.
The overall programme of investment for 2025/26 -
2027/28 as set out in the list of schemes (Appendix 2) were
approved. The projects were summarised in the list of schemes
section as a live document that establishes programmes both funded
and unfunded where they aim to deliver existing Hackney
policy.
REASONS FOR DECISION
In addition to being a legal requirement to
prepare the Local Implementation Plan, the LIP is a key means by
which TfL allocates funding to the Council to deliver transport
projects and programmes. LIP delivery plan 2025/26 - 2027/28 in
Form A outlines the programmes and projects the Council proposes to
deliver from April 2025 to March 2028.
TfL issued guidance for boroughs to assist
them in preparing their LIP delivery plans 2025/26 - 2027/28 in
July 2024. As part of this TfL indicated the timescale for
preparing the LIP delivery plan 2025/26 - 2027/28 as follows:
TfL submission timeline:
Date
Milestone
July
2024
Final
LIP Guidance published
15
November 2024
Borough deadlines for draft submissions
09
January 2025
TfL
provide informal feedback on submissions
13
February 2025
Deadline for borough final submissions to TfL
13
March 2025
TfL
funding letters to boroughs
DETAILS OF ALTERNATIVE OPTIONS CONSIDERED AND
REJECTED
Preparing a LIP delivery plan 2025/26 -
2027/28 is a requirement set out by TfL to apply for LIP funding.
Not doing so would greatly reduce Hackney’s ability to meet
the outcomes of the Local Implementation Plan.
Other sources of funding are bid for when they
become available and are used to supplement the LIP or deliver
additional schemes that meet the same outcomes as set out in the
list of schemes in this document.
Related Meeting
Cabinet - Monday 27 January 2025 6.00 pm on January 27, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 27 Jan 2025 |