Project Appraisal - Bramley Village Improvements
February 27, 2025 Director of Universal Services (Officer) Approved View on council websiteFull council record
Content
1. That the Director of Universal Services
approves the Project Appraisal for Bramley Village Improvements, as
outlined in this report.
2. That the Director of Universal Services gives approval to
procure, spend and enter into necessary contractual arrangements,
in consultation with the Head of Legal Services, to implement this
scheme, at a total estimated cost of £487,000, to be funded
from S106 funding.
3. That the Director of Universal Services and the Head of Legal
Services progress orders, notices, statutory procedures and secure
and enter into all appropriate agreements, licences, consents,
permissions, rights or easements necessary to enable implementation
of the scheme.
Details
| Outcome | Recommendations Approved |
| Decision date | 27 Feb 2025 |