Contract Award – Fire Safety and External Refurbishment Works in 198-209 Spencers Croft, 25-36, 37-48, 49-60 and 98-109 Little Cattins, 2-73 and 83-124 The Stow, and 63-74 Blackbush Springs
November 18, 2025 Deputy Leader and Portfolio Holder for Housing (Cabinet member) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to award contracts for fire safety and external refurbishment works to Durkan Limited for The Stow and Little Cattins, and to Chas Berger Ltd for Spencer's Croft and Blackbush Spring, totaling £3,320,706.88 + VAT, to ensure compliance with fire safety regulations and improve housing quality standards.
Full council record
Decision
RESOLVED that:
A
Approval is given to award the contract for the Fire Safety and
External Refurbishment Works at The Stow to Durkan Limited for the
total sum of £701,779.36 + VAT, in accordance with the
Procurement Act 2023 for below-threshold works contracts.
B
Approval is given to award the contract for the Fire Safety and
External Refurbishment Works at Little Cattins to Durkan Limited
for the total sum of £1,361,504.37 +
VAT, in accordance with the Procurement Act 2023 for
below-threshold works contracts. The contractor will be engaged
using the JCT Intermediate Building Contract (2024) with
Contractor’s Design, and the Council’s standard
Schedule of Amendments.
C
Approval is given to award the contract for the Fire Safety and
External Refurbishment Works at Spencer’s Croft to Chas
Berger Ltd for the total sum of £777,744.33+ VAT, in
accordance with the Procurement Act 2023 for below-threshold works
contracts.
D
That approval is given to award the contract for the Fire Safety
and External Refurbishment Works at Blackbush Spring to Chas Berger
Ltd for the total sum of £479,677.82 +
VAT, in accordance with the Procurement Act 2023 for
below-threshold works contracts.
Reasons for the decision
The decision is proposed to enable the
delivery of essential FRA remedial works to bring the
Council’s housing stock in line with statutory fire safety
requirements, maintain housing quality standards, and ensure
completion ahead of the statutory March 2026 compliance
deadline.
Alternative options considered
As set out in the reports attached as
appendices A, C, E, and G.