Contract Award - Roofing Works at 19-36, 87-102 and 111-127 Peterswood

November 20, 2025 Deputy Leader and Portfolio Holder for Housing (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to resolve water ingress and ensure regulatory compliance at 19-36, 87-102 and 111-127 Peterswood, a contract worth £618,354.46 was awarded to ETEC Contract Services Ltd., subject to contract and leasehold consultation, utilizing the JCT Intermediate Building Contract (2024) and the Council's standard Schedule of Amendments.

Full council record

Decision

RESOLVED that a contract  be awarded in
the final sum of £618,354.46 to ETEC Contract Services Ltd.
(Company Number 05392794) “subject to
contract and leasehold consultation”. The contractor will be
engaged using the JCT Intermediate Building Contract (2024) and the
Council’s standard Schedule of Amendments.

Reasons for the decision

The required works will resolve the problems
the blocks have had with water ingress and ensure compliance with
Part B and L of the Building Regulations. The work will contribute
to reducing future maintenance needs and improve thermal
efficiency.

Alternative options considered

Do nothing: Withdrawing the work would result in continued
deterioration of the building. While ongoing maintenance would
still be required, key fire safety recommendations would remain
unaddressed, exposing the Council to potential legal non-compliance
with statutory obligations, including:
 
·        
Landlord and Tenant
Act 1985
·        
Homes (Fitness for
Human Habitation) Act 2018
·        
Housing Act 2004
(HHSRS)
·        
Regulatory Reform
(Fire Safety) Order 2005
·        
Building Safety Act
2022
·        
Fire Safety (England)
Regulations 2022
·        
Decent Homes
Standard
 
Partial or Reduced Scope: Undertaking works in phases risks
non-compliance with health and safety legislation and increases
overall costs due to site set-ups, welfare, other contractor
prelims, and management costs. A full package of works offers
greater cost efficiency.

Supporting Documents

Contract Award - Roofing Works at 19-36 87-102 and 111-127 Peterswood.pdf

Details

OutcomeRecommendations Approved
Decision date20 Nov 2025
Subject to call-inYes