RoOD Ridgemoor Windows and Door replacement
February 10, 2025 Service Director - All Ages Commissioning (Other) Approved View on council websiteFull council record
Decision
To award a contract to Joedan Manufacturing
(UK) Ltd. This decision is to award the contract to Joedan
Manufacturing (UK) Ltd to carry out windows and doors replacement
at The Mallards care facility, Hereford, following the completion
of a successful tender, evaluation and moderation process.
Works are to be completed no later than 30 April 2025
To approve the works expenditure of up to £68,433.65.
The responsibility for monitoring the project to be carried out by
the Senior Project Manager within the spend budget.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 10 Feb 2025 |