Decision to approve the expenditure of up to £55,000.00 for the capital emergency drainage works at Peterchurch Primary School
May 8, 2025 Service Director - Education, Skills and Learning (Other) Approved View on council websiteFull council record
Decision
Award a contract to Express Solutions for the
emergency drainage works at Peterchurch Primary School
Herefordshire.
Approve the expenditure of up to £48k for the works, which
includes a
contingency of up to £10k.
Approve the expenditure of up to £7k for internal and
external professional fees.
Responsibility for monitoring the programme to be carried out by
the Capital Senior Project Manager within the spend
budget.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 8 May 2025 |