Decision to approve an Early Works Instruction in respect of Peterchurch Primary School project for early procurement and site mobilisation works
June 16, 2025 Service Director - Education, Skills and Learning (Other) Approved View on council websiteFull council record
Decision
Decision to approve an Early Works Instruction
under the Pre-Services
Construction Agreement in respect of the Peterchurch Primary
School
project for enabling works to be instructed.
The Early Works Instruction 2 will instruct early procurement and
site
mobilisation works at a cost of £168,083.27 due to a long
lead in time and
to ensure there is not a delay to programme, this is within the
budgets set
aside for these elements of the project.
Related Meeting
Licensing Sub-Committee - Monday 4 August 2025 10.00 am on August 4, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 16 Jun 2025 |