Decision to spend from the Property Services Estate Capital Building Improvement Programme 2025/2028 on the care facility emergency programme of works

July 8, 2025 Corporate Director – Economy & Environment (Officer) Approved View on council website
Full council record

Decision

To instruct Hoople Ltd to deliver the
following services/works up to a total
value of £153,425. Works are to be completed no later than 31
March
2026. Works/locations are listed below:
Building Description Total
Southbank
Close
P2 Condition Survey Work( Internal and
External) £34,925.00
Ridgemoor
P2 Condition Survey Work (Internal and
External) £103,500.00
Contingency £15,000.00
TOTAL £153,425.00
Authority is delegated to the Senior Project Manager from the
Corporate Director – Economy & Growth to act as spend
manager for the
project.

Supporting Documents

Care Home Emergency Works Hoople ROOD- Phase 2.pdf

Details

OutcomeRecommendations Approved
Decision date8 Jul 2025