Decision to accept a Surrender from National Grid of a lease of land (electricity substation) located adjacent to Halo leisure pool and council’s Pay & Display car park at St Martin’s, Hereford

March 5, 2026 Commercial and Investment Manager (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to accept the surrender of National Grid's lease for an electricity substation near Halo leisure pool and the council's car park at St Martin's, Hereford, to facilitate the installation of new high-speed car charging points.

Full council record

Decision

Decision to accept a Surrender from National
Grid of a lease of land (electricity substation) located adjacent
to Halo leisure pool and council’s Pay & Display car park
at St Martin’s, Hereford
• A new substation is necessary to supply the voltage
requirements of new high speed car charging points in the public
car park, that are already installed.
• The legal process requires the lease of the old substation
site to be surrendered.
• A new transaction will be completed for the new site and
will be covered by a separate decision

Supporting Documents

RoOD - Surrender of NG lease at St Martins car park Hereford SG P.pdf

Details

OutcomeRecommendations Approved
Decision date5 Mar 2026