Decision to award contract and approve the expenditure of up to £229,454.84 for the internal refurbishment works of two existing classrooms at St Martins School, Hereford.
May 15, 2026 Service Director - Education, Skills and Learning (Other) Approved View on council websiteFull council record
Decision
Award a contract to SC Joseph for the internal refurbishment works of two existing classrooms at St Martins Primary School, Hollybush Walk, Hereford HR2 6AF, following a successful tender on the Council’s procurement portal.
Approve the expenditure of up to £218,528.84 for the works, which includes a contingency of up to £19,275.35
Approve the expenditure of up to £10,926 for internal and external professional fees.
Responsibility for monitoring the Programme to be carried out by the Capital Project Manager within the spend budget.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 15 May 2026 |