Award a contract to Jackwolf Group and approve the expenditure of up to £415,274 for the provision of heating works required at Ashfield Park Primary School.

March 12, 2026 Service Director - Education, Skills and Learning (Other) Approved View on council website
Full council record

Decision

Award a contract to Jackwolf Group for the heating upgrade works
required at Ashfield Park Primary School, Ross-on-Wye, Herefordshire.

Approve the expenditure of up to £370,629.90, which includes a 10%
contingency of £33,693.62 (works value is £336,936.27)

Approve the expenditure of up to £44,644.05 for external and internal
fees.

Responsibility for monitoring the programme to be carried out by the
Capital Project Manager within the spend budget.

Supporting Documents

Ashfield Park School Heating.pdf

Details

OutcomeRecommendations Approved
Decision date12 Mar 2026