Extension of the Payment Cards for Direct Payments
February 22, 2024 Service Director - All Ages Commissioning (Other) Approved View on council websiteFull council record
Purpose
An extension is required for an additional 2
months of the extended 5 year plus 8 months contract with Prepaid
Financial Services (PFS) which is due to end on 31st March 2024 due
to complications on-boarding to the new provider following the
re-commissioning exercise.
The nature of financial regulations and compliance has changed,
resulting in new fixed timescales which were not known at the time
of contract award to the new provider. This extended period would
allow the council to meet these compliance timeframes and reduce
the impact on the council’s current customers of
approximately 1,000 cardholders.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 22 Feb 2024 |