High Needs Capital Grant: Barrs Court School (Phase 2)

January 24, 2024 Corporate Director - Children & Young People (Officer) Approved View on council website
Full council record

Purpose

To approve spend from the High Needs Provision
Capital Grant to undertake further improvement works at Barrs Court
School.

Decision

That:
 
a) Subject to
planning consent and the £50,000 contribution from Barr Court
School, that up to, £344,600 from the High Needs Provision
Capital grant is allocated to undertake 
improvement work at Barrs Court School
(total budget £394,600);
 
b) The Service
Director for Education, Development and Skills will be authorised
to take all operational decisions necessary to deliver the
works

Supporting Documents

High Needs Capital Grant Barrs Court School Phase 2 main report.pdf

Details

OutcomeRecommendations Approved
Decision date24 Jan 2024
Subject to call-inYes