To award a contract to provide consultancy services for the Expansion at Aylestone High School – appointment of Project Manager led Multi-Disciplinary Team.
October 2, 2023 Corporate Director - Children & Young People (Officer) Approved View on council websiteFull council record
Purpose
Additional capacity is required to meet growing numbers in the
north of the city and following on from feasibility work, a
decision has been approved for additional capacity at Aylestone
School, which will relieve the overall pressure in the north of the
city.
A feasibility study was commissioned to identify what opportunities
there are at the school to expand. The study identified that the
increase in capacity causes the school to be under-provided for
accommodation in several areas: under-provided and under-sized
general and specialist teaching spaces, an under provision of a
suitable sports hall and under provision of administration, storage
and toilet areas.
This project chiefly addresses the need for the required additional
spaces, through some remodelling and a new build teaching block and
sports hall which will be designed and built in such a way that it
can be added to in the future.
During this stage, the project management led team will act as a
client agent/representative for the duration of the project, RIBA
Stages 2-6, with the new build and remodelling being delivered
under a Design & Build (D&B) contract.
The appointment will include for preparing relevant tender
documents and evaluations for the appointment of a contractor under
a D&B contract for the construction of the new build areas and
remodelling of the school.
Gleeds Management Services LTD have been selected following a
competitive tendering exercise in accordance with the