Hereford Western Bypass Phase 1 – Release of Development Funding
July 9, 2026 Corporate Director – Economy & Environment (Officer) Awaiting outcome View on council websiteFull council record
Decision
To progress additional pre-construction works to keep the
project on agreed programme.
To spend on utilities (surveys, making safe and moving where
required) ensuring that the planned construction work doesn’t
adversely impact the critical utilities in the area.
To extend professional services with AECOM providing
critical design advice and technical overview of the emerging
works.
Supporting Documents
Details
| Outcome | For Determination |
| Decision date | 9 Jul 2026 |