Decision to spend from the Property Services Estate Capital Building Improvement Programme 2024/2027 on the care facility emergency programme of works
May 13, 2024 Director of Resources and Assurance (Historic) (Officer) Approved View on council websiteFull council record
Decision
To instruct Hoople Ltd to deliver the
following services/works up to a total value of £237,198.50
(including fees and contingency). Works are to be completed no
later than 31 March 2025. Works/locations are listed below:
South Bank Close, Ridgemoor and Hillside
New Furnishings & Beds
£24,442.00
South Bank Close
P1 from Condition Survey
£27,775.00
Ridgemoor
P1 from Condition Survey
£38,329.50
Ridgemoor
Fire Door Remedial Work
£59,994.00
South Bank Close
Fire Door Remedial Work
£73,326.00
South Bank Close
Enclose Server cabinet in fire resisting enclosure or relocate out
of escape route
£2,222.00
South Bank Close
Improvement work to external fire exit areas
£11,110.00
Total: £237,198.50
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 13 May 2024 |