Phase 1 plots and infrastructure, Ross Enterprise Park – Drawdown of construction and consultancy costs from within approved budget.

October 1, 2026 Service Director Economy and Growth (Other) Approved View on council website
Full council record

Decision

Allow drawdown of cost below within the overall budget approved:
•£750,000 for Construction of Ross Enterprise Park Phase 1 plots and infrastructure to the Principal Contractor, Fitzgerald Contractors Ltd. to allow for unforeseen changes in project scope and programme i.e. ‘compensation events’.
•£255,000 for Consultancy and design services associated with extension of consultancy contracts with Rider Levett Bucknell, SMS Energy Services Ltd and ONE Creative Environments Ltd to 31 October 2026 and additional requirements
•£475,000 for statutory undertaker (utility) fees.

Supporting Documents

RoOD Ross Enterprise Park - Drawdown of construction and consultancy costs.pdf

Details

OutcomeRecommendations Approved
Decision date1 Oct 2026