Phase 1 plots and infrastructure, Ross Enterprise Park – Drawdown of construction and consultancy costs from within approved budget.
October 1, 2026 Service Director Economy and Growth (Other) Approved View on council websiteFull council record
Decision
Allow drawdown of cost below within the overall budget approved:
•£750,000 for Construction of Ross Enterprise Park Phase 1 plots and infrastructure to the Principal Contractor, Fitzgerald Contractors Ltd. to allow for unforeseen changes in project scope and programme i.e. ‘compensation events’.
•£255,000 for Consultancy and design services associated with extension of consultancy contracts with Rider Levett Bucknell, SMS Energy Services Ltd and ONE Creative Environments Ltd to 31 October 2026 and additional requirements
•£475,000 for statutory undertaker (utility) fees.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 1 Oct 2026 |