To award a contract to Speller Metcalfe Malvern Ltd and approve the expenditure of the construction budget for the programme of capital improvements to Brookfield Special School, Herefordshire

June 17, 2024 Corporate Director - Community Wellbeing (Officer) Approved View on council website
Full council record

Decision

a) To appoint and award a contract to Speller
Metcalfe Malvern Ltd for the construction of new sports hall,
stand-alone two class teaching block and internal alterations at
Brookfield School, Hereford, following a successful tender on the
council’s procurement portal for the contract value of
£4,566,783.00.
b)

FUNDING BUDGET (Max)
DFE Contribution £4,054,236
HC Contribution £1,767,000
£5,821,236

BREAKDOWN OF BUDGET
Construction £4,566,783
Enabling works £95,000
All other project expenses £698,230
Contingency £461,223
Total £5,821,236

Responsibility for monitoring the programme to be carried out by
the Capital Senior Project Manager within the spend budget.

Supporting Documents

Brookfield - RoOD to appoint Speller Metcalf Malvern Ltd and construction budgetv5 003.pdf

Details

OutcomeRecommendations Approved
Decision date17 Jun 2024