Decision to contract award for Riba stage 1 & 2 for the Student Accommodation Feasibility

October 11, 2024 Corporate Director – Economy & Environment (Officer) Approved View on council website
Full council record

Decision

To award a Pre-Development agreement to
Cityheart ltd to complete Riba
stage 1 & 2 on the viability of Student Accommodation on the
Edgar Street Football Stadium site and the College Road Campus
Site.
Approve the expenditure of up to £253,679.00.
Responsibility for monitoring the Feasibility to be carried out by
the Senior Project Manager

Supporting Documents

RoOD - RIBA Stage 1 2 Feasibility Student Accommodation.pdf

Details

OutcomeRecommendations Approved
Decision date11 Oct 2024