OD/22/182 Hawke Road Play Area

April 21, 2023 Officer Decision (Officer) Approved View on council website
Full council record

Purpose

On 8 February 2022, Executive authorised
funding for a new five year £3.5m investment programme in
play areas (including additional funding from Section 106 planning
agreements)
 
On 8 March 2022, Executive adopted the Play
Area Strategy 2022 - 2027 and Play Area Action (Investment) Plan
2022 - 2027 and that the Parks and Cemeteries Operations Manager be
authorised to take all necessary steps to deliver the improvement
works necessary and replace the play areas identified.
 
Hawke Road Recreation Ground Play Area is
identified as a site to be replaced in 2022 – 2024.

Decision

The decision made was to award a contract to
Kompan Ltd.
 
Reason:
For the supply of play equipment and
associated safety surfacing.

Supporting Documents

OD-22-182 Hawke Road Play Area.pdf

Details

OutcomeRecommendations Approved
Decision date21 Apr 2023