Full council record
Purpose
Following a number of technical and financial
reviews the council is seeking to best understand the options and
recommendation for future operating models for the chain ferry
crossing at East Cowes / Cowes across the mouth of the River
Medina.
This report sets out the process of commissioning an options
appraisal and a potential Commissioning Strategy for alternative
technical and economical solutions to the current vessel operated
by the council.
Content
Cabinet agrees and resolves to replace the
current floating bridge. Cabinet agrees to accept the
recommendations set out in the Cabinet report as an indicative
process.
Utilising previous work carried out in respect
of the floating bridge over recent years, Cabinet agree that this
information should be used to inform the next stage to ensure the
necessary work is carried out as quickly and efficiently as
possible.
This will include working with the consultants
“3S”, who have supported the recent review and who have
extensive knowledge of the process and background. 3S will
positively support the stated aim and project to replace the
floating bridge going forward.
The scope of their work is to be agreed
between Cabinet, officers and 3S.
Details
| Outcome | Recommendations Approved |
| Decision date | 14 Mar 2024 |
| Subject to call-in | Yes |