CAPITAL OUTTURN 2024/2025
July 24, 2025 Cabinet (Cabinet collective) Awaiting outcome View on council websiteFull council record
Content
RESOLVED: Cabinet:
1. noted the outturn of the capital programme
for 2024/2025 of £39,656,557 including Exempt Schemes;
2. noted the financing arrangements for the
2024/2025 capital programme;
3. Approved the commencement of spend by
moving project from tier 3 to tier 2 (paragraph 9.1)
4. Approved reallocation of budget to new
project at tier 2. (paragraph 9.2)
REASON FOR DECISION: To report
the outturn 2024/2025 for the Capital Programme and receive an
update to the Capital Programme 2024/2029.
Related Meeting
Additional Meeting, Cabinet - Thursday, 24th July, 2025 6.00 pm on July 24, 2025
Details
| Decision date | 24 Jul 2025 |