Our Cultural Heart (OCH). Phase 1 - Extend the Pre-Construction Services Agreement (PCSA) period - Instruct further internal demolition works under the PCSA
June 7, 2024 Strategic Director for Growth and Regeneration (Officer) Approved View on council websiteFull council record
Purpose
The contractor (BAM) is
already working under the PCSA to deliver the RIBA 4 stage design,
negotiate the NEC construction contract and the associated contract
sum and carry out the already instructed enabling works.
The PCSA period is to be
extended by five weeks to the 12th July 2024 to allow
the construction contract and the associated contract sum
negotiations to be concluded.
At the same time, to utilise
the contractor resources efficiently and to maintain the programme,
further internal demolition works are to be instructed under the
PCSA. These works are part of the demolition works that were
intended to be carried out during the next stage of the delivery
programme under the NEC construction contract.
Funding of £348,093 to
cover both these items will be drawn from the approved construction
stage budget.
This decision takes effect
from the 7th June 2024.
Background information
https://democracy.kirklees.gov.uk/documents/s54749/Signed.%20OCH%20GW4%20Cabinet%20Report%2021.12.23%20public.pdf
Content
To extend the PCSA period to
the 12th July 2024 and to instruct further internal
demolition works under the PCSA as part of the enabling
works.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 7 Jun 2024 |