Summary
... to approve a waiver to the council's Contract Standing Orders to directly award a £240,000 contract to Energy Specifics for completing decarbonisation works on five social housing properties between December 2025 and March 2026.
Full council record
Decision
To approve a waiver to the
council’s Contract Standing Orders 17.2(d) to directly award
a contract to Energy Specifics to deliver the outstanding works at
a value of £240K to complete works to the remaining five
properties in various wards over a 16-week period, commencing 1
December 2025 to 31 March 2026.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 19 Nov 2025 |