Brockwell Park to Gipsy Hill Healthy Route Extension (Phase 3) and West Dulwich Controlled Parking Zone (CPZ) - Results of Statutory Consultation

January 14, 2026 Deputy Leader of the Council (Sustainable Lambeth and Clean Air) (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Deputy Leader of the Council (Sustainable Lambeth and Clean Air) approved recommendations on 14/01/2026. The decision authorised the making of traffic management orders for the Brockwell Park to Gipsy Hill Healthy Route Phase 3 extension and limited elements of the West Dulwich Controlled Parking Zone. The decision also approved a projected spend of £974,000 for the Healthy Route and specific parking changes.

Full council record

Purpose

To consider the responses received through
statutory consultation, and subsequent recommendations.

Decision

1.         
To carefully consider the results of the consultation undertaken
between 9 August and 20 September 2024 in respect of the proposals
referred to in this report, including formal objections received
during the statutory consultation period (presented in Appendices A
and B) and officers’ responses to these representations
(Appendices C and D).
 
2.         
In accordance with the council’s statutory duties under the
Equality Act 2010, including the Public Sector Equality Duty, to
carefully consider the Equality Impact Assessments (EIAs)
(Appendices E and F) prepared in respect of the proposals referred
to in this report.
 
3.         
To note scheme approval provided by the Phase 3 Transport Programme
– Capital Drawdown report of 10/09/2024 for the Brockwell Park to Gipsy Hill Healthy Route as illustrated
in Appendix G1, subject to commencement by Spring 2026.
 
4.         
Further to recommendation 3 above, to authorise the making of
traffic management orders to introduce all measures relating to the
Phase 3 extension of the Brockwell Park to Gipsy Hill Healthy Route
(between the A205 South Circular and Park Hall Road) and to
implement limited elements of the proposed Controlled Parking Zone
(CPZ) scheme as shown in the plan in Appendix G2.
 
5.         
Following the outcome of statutory consultation, to exercise
discretion to not hold a public inquiry pursuant to Regulation 9 of
the Local Authorities Traffic Orders (Procedure) (England and
Wales) Regulations 1996.
 
6.         
To note that further consideration and review is required for the
remaining elements of the CPZ, not proposed as part of this report,
which will be decided on at a later date.
 
7.         
To approve the projected spend of £974,000 (detailed in Table
3) to install the Healthy Route and specific parking changes to be
funded with Local Implementation Plan (LIP) funding, allocated by
TfL.
 
8.         
To authorise a statutory consultation to take place in early 2026
on the proposed parklets as detailed in Appendix L under section
115G of the Highways Act 1980 and that if, by the end of a 28-day
consultation period, no objections have been received the parklets
be implemented, but if objections are received, then the Assistant
Director of Parking, Network Management and Fleet be delegated in
consultation with the Deputy Leader of the Council (Sustainable
Lambeth and Clean Air) to consider the representations and decide
on whether to implement or abandon the proposals.

 
 

Supporting Documents

CMDDR Brockwell Park to Gipsy Hill Healthy Route Extension Phase 3 and West Dulwich Controlled Pa.pdf
Appendix B - CPZ Statutory Consultation Representations.pdf
Appendix C - HR Representation themes and responses.pdf
Appendix D - CPZ Representation themes and responses.pdf
Appendix F - Parking control and sustainable measures EIA.pdf
Appendix G1 - Healthy Route Phase 3 Design.pdf
Appendix H - Rosendale Road junction consultation report.pdf
Appendix J1 - West Dulwich leaflet.pdf
Appendix K - CPZ Detailed Design Plan.pdf
Appendix M - West Dulwich Informal Consultation Results.pdf
Appendix O - West Dulwich CPZ Stat Cons Leaflet.pdf
Appendix A BP-GH Healthy Route Phase 3 Representations.pdf
Appendix I - BP-GH Healthy Route - consultation report 2021.pdf
Appendix E - BP-GH Healthy Route Phase 3 EIA.pdf
Appendix J2 - FAQs.pdf
Appendix L - West Dulwich Parklets.pdf
Appendix G2 - parking and kerbside measures.pdf
CMDDR Brockwell Park to Gipsy Hill Healthy Route Extension Phase 3 and West Dulwich Controlled Pa.pdf

Details

OutcomeRecommendations Approved
Decision date14 Jan 2026
Subject to call-inYes