Approval of Additional Capital Allocation for the Construction of a Resource Centre for Adults with Learning Difficulties at Coburg Crescent.
June 4, 2024 Director of Highways, Environment and FM (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to allocate £425,090 from unallocated capital contingency and approve a £366,096 contract increase with Farrans for the construction of the new Adult Social Care Resource Centre at Coburg Crescent.
Full council record
Decision
1.
To allocate £425,090 from the unallocated
capital contingency “theme” to the Coburg Crescent
scheme.
2.
To approve an increase of £366,096 to the
value of the contract with Farrans for the construction of
the new Adult Social Care Resource Centre to be
effective in May 2024.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 4 Jun 2024 |