Fireproofing and Compartmentation (FRA) Programme (Boroughwide)

August 15, 2024 Deputy Leader of the Council (Housing, Investment and New Homes) (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to appoint Trail Group Ltd for fireproofing and firestopping works via the Pretium Framework, with an initial contract value of £1,500,000 and potential extensions up to £2,500,000, and to approve an additional £350,000 for loft insulation works.

Full council record

Purpose

The proposed works will be procured through
Pretium Framework - Lot 5A - 5E Fire Proofing and Compartmentation
Works.
The principal area of works to be completed will be the
installation of new fire proofing and compartmentation in loft
spaces that do not meet with the current fire safety standards
and/or building regulations.

Decision

1.    
To approve the appointment of Trail Group Ltd to Lot 5 -
Fireproofing and Firestopping works via the Pretium Framework at an
annual contract value of £500,000 commencing in September
2024 and running until August 2027, the total sum for the initial
years being £1,500,000, with two possible further extensions
of one year each making the total contract value £2,500,000
to 2029.
 

2.    
To approve an additional £350,000 one-off payment to deliver
loft insulation works allocated from carbon offset fund.
 

Supporting Documents

Appendix A - EqIA.pdf
CMDDR Fireproofing and Compartmentation FRA Programme Boroughwide.pdf

Details

OutcomeRecommendations Approved
Decision date15 Aug 2024
Subject to call-inYes