Sudbourne Primary School Settlement of Final account

October 21, 2024 Cabinet Member for Children, Young People and Families (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve a £912,596.70 budget increase for the Sudbourne Primary School project to settle the final account and a contract variation of £862,596.70 with Farrans Construction.

Full council record

Decision

1.         
To approve the increase in the project budget for
Sudbourne Primary School by
£912,596.70 in order to pay retention costs and to settle the
Final Account, which includes a sum of £50,000 to pay
associated professional services and staffing costs detailed in the
Part II of this report. The construction works at Sudbourne Primary School commenced in January 2020
and are due to be completed by 31 December 2024.

 

2.         
To approve the variation to the JCT Design and Build
contract (2011) with the principal contractor for the works,
Northstone (NI) Limited t/a Farrans
Construction, for the sum of £862,596.70.
 

Supporting Documents

Sudbourne CMDDR Part I.pdf
EIA.pdf

Details

OutcomeRecommendations Approved
Decision date21 Oct 2024
Subject to call-inYes