Road Danger Reduction Programme

October 15, 2024 Corporate Director: Resident and Enabling Services (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve the Road Danger Reduction Programme, including granting scheme approval for proposals outlined in the report, authorising statutory consultations and notices, and delegating authority regarding potential local inquiries, all with consideration of an Equality Impact Assessment.

Full council record

Decision

1.         
To grant scheme approval for the proposals described
in section 2 of this report and illustrated in the design drawings
attached in Appendices B and C at an estimated cost of
£256,393.59 from April 2024 to March 2025.

2.         
To have regard to the Equality Impact Assessment
prepared for the purposes of this report (Appendix D).

3.         
To authorise officers to carry out statutory
consultation in Rodenhurst Road
and Emmanuel Road
as described in section 2 of the report and as shown
in Appendices B and C to amend parking restrictions
under Regulation 6 of the Local Authorities Traffic
Orders (Procedure) (England and Wales) Regulations 1996 and
and to authorise officers to issue statutory notices
for proposed road humps under Section 90C of
the Highways Act 1980 and to authorise officers to issue a statutory notice for a new pedestrian crossing
under section 23 of the Road Traffic Regulation
Act.

4.         
To implement the scheme and make a permanent traffic
management orders under sections 6, 45, 49, 124 and Schedule 1 and
Part IV of Schedule 9 of the Road Traffic Regulation Act 1984;
should no material representations be received during the statutory
consultation process, but that if any objections or representations
are received, they are considered by the Corporate Director for
Resident and Enabling Services by way of a written report before a
decision is reached. 

5.         
That, subject to the consideration of the written
report referred to in recommendation 4 above, to delegate to the
Director of
Highways, Environment and FM authority to consider whether or
not to hold a local inquiry in respect of objections resulting from
the statutory consultation process under section 90C of the
Highways Act 1980 as referred to at paragraph 4.17 of this
report.

6.         
To exercise discretion not to hold a public inquiry
pursuant to Regulation 9 of the Local Authorities Traffic Orders
(Procedure) (England and Wales) Regulations 1996.

 
 

Supporting Documents

Appendix C - Emmanuel Road Zebra Crossing General Arrangement.pdf
Appendix D - Schemes Equalities Impact Assessment.pdf
ODDR - Road Danger Reduction Programme.pdf
Appendix A - Sinusoidal Road Hump and Speed cushion standard details.pdf
Appendix E - Map Locations for proposed schemes.pdf
Appendix B - General Arrangement Drawings for Rodenhurst Road.pdf

Details

OutcomeRecommendations Approved
Decision date15 Oct 2024