Transpennine Route Upgrade – Transport and Works Act Order (TWAO) Objection Update

Director of City Development (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

... whether to withdraw the formal objection to the Transpennine Route Upgrade Transport and Works Act Order, endorse the Statement of Common Ground, approve entering into the Environmental and Highways Agreements, approve the revised Deemed Planning Conditions, and approve entering into a Funding Agreement with Network Rail.

Full council record

Decision

In accordance with the Full Council resolution
of 15th November 2023 the Director of City Development
approved:

a) The withdrawal of the formal objection on the agreed matters in
the Statement of Common Ground (as per Appendix A)
b) noted the issues that have not been resolved, held within the
Council's Statement of Common Ground (Appendix A) and may be
identified as ‘matters’ by the Inspector to be
determined at the public inquiry scheduled to commence on 27th
February 2024.
c) endorsed the Statement of Common Ground.
d) approved entering into the Environmental Agreement (appendix C)
and Highways Agreement (appendix B) on the terms set out in the
report.
e) approved the revised Deemed Planning Conditions (appendix
D)
f) approved entering into a Funding Agreement with Network Rail to
meet the cost of officers supporting the implementation of the
TWAO.

Supporting Documents

APPENDIX E.pdf
REPORT TO THE DECISION MAKER.pdf
SIGNED DECISION RECORD.pdf
APPENDIX A.pdf

Details

OutcomeRecommendations Approved