Kirkgate Market 1875 Blockshops Phase 2
January 10, 2024 Director of City Development (Officer) Key decision Awaiting outcome View on council websiteFull council record
Purpose
The Director of City Development is requested to authorise expenditure to complete works on Phase 1 and carry out the second and final phase of construction on the 1875 Blockshops at Kirkgate Market.
Decision
The Director of City Development has authorised total expenditure of £7,763,500. This consists of £1,640,000 for the retrospective fee approvals, essential variations and other costs required to complete phase 1, and £6,123,500 for phase 2 fees and costs including the tender sum of £5,387,000 submitted by Bermar Building Co Ltd. Works funded from existing budget provision (capital scheme 33077).
Details
| Decision date | 10 Jan 2024 |
| Effective from | 18 Jan 2024 |
| Subject to call-in | Yes |