Capital Funding for VxRail Hardware Replacement
October 13, 2025 Chief Operating Officer - Jacqui McKinlay (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to fund the replacement of VxRail hardware, she approved the virement of £0.400M from the approved capital budget for SDWAN Implementation (BPWSD10) that was approved in Cabinet in October 2024, noting that this was a budget reallocation and not approval for new procurement.
Full council record
Decision
For the reasons set out in the report, it is
recommended to:
Approve the virement of
£0.400M of approved capital budget (approved in Cabinet
October 2024) from capital code BPWSD10 (SDWAN
Implementation) to fund this investment. This request is for
budget reallocation only and is not approving any new
procurement.
Alternative options considered
1.1
Work to maximise the use of cloud is online, and only those
workloads and applications which cannot be moved to cloud will
require the Council to retain a physical server
estate.
1.2
Do nothing is not an option as the current platform is at the end
of its service life. Once all workloads have been specified
for cloud migration, the scale of requirement will be fully
understood, this will inform the scale and size of the required
expenditure.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 13 Oct 2025 |