Variation of Application Hosting Contract
October 27, 2025 Chief Operating Officer - Jacqui McKinlay (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve the award of a contract for Application Hosting, Backup, Recovery and Implementation Services to the highest scoring bidder for five years, with an option to extend for three, at a cost of £3.147m.
Full council record
Decision
For the reasons set out in this report, the
Director has decided to:
1)
Approve the variation of contract DN753421: Application Hosting,
Backup, Disaster Recovery and Implementation Services with Phoenix
Software Ltd to include the provision of a managed firewall service
requirement commencing in November 2025 to the contract end date of
31 March 2030 at a cost of £205.3k (exc VAT).
Alternative options considered
Proceed without incorporating the detailed
service specification into the contract. This would present a risk
to the Council’s ability to effectively manage the supplier
without defined service levels, key performance indicators, terms
and conditions; meaning exposure to a degraded level of service and
increased security risk.
Retender the service. Would significantly impact the delivery of change,
increasing cost, prevent / delay the vacating of Premier Court
Datacentre.