Bowring Park Viaduct - Structural Assessment
February 27, 2026 Corporate Director Neighbourhoods and Housing - Nicki Butterworth (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...approve the commencement of a procurement process to identify and appoint a contractor to undertake a structural assessment of Bowring Park Viaduct.
Full council record
Purpose
Structural Assessment of Bowring Park
Viaduct
Decision
For the reasons set out in this report, the
Corporate Director has decided to:
1)
Approve the commencement of a procurement process to identify and
appoint a contractor to undertake a Structural Assessment of
Bowring Park Viaduct for an estimated period of February 2026 to
August 2026 with an option to extend for a further 2 months at no
further cost.
Alternative options considered
Direct Award – Direct Award could
reduce the competitiveness of the price alongside not being a
compliant Procurement. This option has
therefore been discounted.
Do Nothing – A Do Nothing option
would put the Council at significant financial risk. The detailed design and associated site works
could have significant delays with delay costs associated, as a
competent contractor would place significant risk associated with
any concrete repair works to a Post Tensioned Structure without a
valid Structural Assessment. This
option has therefore been discounted.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 27 Feb 2026 |