Agreement to Lease Commercial Space -Maidstone East

October 21, 2026 Cabinet (Cabinet collective) Key decision Approved View on council website
Full council record

Purpose

To seek approval for the Council to grant a commercial lease of the commercial space within the Maidstone East development to the NHS for the delivery of an integrated health facility. The lease would be granted at a peppercorn rent, with no rental income payable to the Council.

The commercial rationale is that the NHS would meet the works cost and all fit-out costs required to deliver the facility. This would secure a long-term public health use within the development, support the wider regeneration objectives for Maidstone East and reduce the amount of capital the Council would otherwise need to contribute to the scheme.

Reasons for the decision

Maidstone East is a mixed-use regeneration scheme comprising 180 new homes, public open space, public realm improvements and approximately 1,863m² (20,000 sq ft) of commercial accommodation.

The Council has been working with NHS partners on the opportunity to use the commercial space for an integrated health facility. The proposed facility would support primary, community and neighbourhood health services for the local population.

Discussions with NHS Kent & Medway Integrated Care Board (ICB) have progressed significantly from initial conversation many years ago, with the NHS now looking to develop a business case to occupy the entirety of the commercial floorspace as an integrated healthcare hub serving both new residents and the wider community.

The proposal aligns with the original vision for the development, which included the aspiration to deliver a healthcare facility as part of the wider regeneration of the area. NHS partners have confirmed support for the project and are progressing the approvals required to secure capital funding.

Progress on the healthcare proposal has advanced significantly during the last twelve months. The NHS Strategic Outline Case has received internal support and the NHS capital funding requirement has been identified to support delivery of the facility.

Proposed Commercial Structure

The council will fund the works to deliver the commercial unit to shell and core (as per the cost highlighted at Fig H of Appendix 1) which is in excess of the current valuation of the commercial space, a further benefit of the proposed funding arrangement. The Council will also manage the fit out of the space to the required specification of behalf of the NHS. The Council will recover all associated works and fit out costs to the commercial space, from the NHS, handing over a fully functional health care facility. These costs represent a significant portion of the overall scheme costs.

In return the Council will grant a long leasehold interest of the commercial space to the ICB at a peppercorn rent. The Council would not receive a traditional rental income from that commercial space but would benefit overall by having the build cost and fit out cost covered in full by the ICB.

The NHS would occupy the entirety of approximately 1,863 square metres of commercial accommodation within the development. The Council will retain ownership of the commercial accommodation, as freeholder, and grant a leasehold interest to the NHS, securing a long-term healthcare use whilst maintaining the Council's ownership of the asset.

The arrangement would secure the NHS as the occupier of the commercial space and enable the delivery of a long-term integrated health facility as part of the Former Royal Mail Sorting Office redevelopment.

Financial Implications

Under the arrangement, the council would receive a reduced level of rental income from the commercial space, compared with a full market rent, however the NHS, as stated above, will fully reimburse MBC for all cost associated with delivering the health care facility. This reduces the Council’s overall capital requirement needed to deliver the wider mixed-use redevelopment.

The Council could otherwise seek a full market rental income from the commercial space. However, the proposed NHS arrangement offers a different form of value for money as well as significant social value improvements to the area and those facilities.

The peppercorn rent reflects the fact that the NHS would fund the delivery of the health facility rather than pay a market rent. The arrangement should therefore be considered in the round, balancing the absence of rental income against the reduced capital requirement and the wider public benefit of securing a healthcare use.

The proposal also reduces uncertainty around the commercial space by identifying a long-term public sector occupier and a community use that is complementary to the residential and public realm elements of Maidstone East.

The proposal also improves the overall viability of the Maidstone East development by securing substantial third-party investment into the commercial element of the scheme. The financial benefits of the arrangement have been reflected within current viability and financial modelling assumptions for the wider project.

The funding sums identified in Exempt Appendix 1 would be secured via an MOU and Section 2 agreement between MBC and the NHS. This includes:

•  A base level of Capital funding available Fig A.

•  Desing fees required to support the NHS Business Case Fig B.

•  Potential further design fees for further architectural work Fig C

•  Total NHS funded Capital Package paid to MBC up to Fig D in Appendix 1

•  A Contribution of CIL Funding as per Fig. E, as secured in the Cabinet Report “CIL Bidding Round 2 Allocations 22nd July 2026

•  A contribution of S106 monies as per Fig. F.

This provides a total funding package to be paid from the NHS to MBC to cover the build and fit out works and associated design fees of up to the value of Fig. G of Exempt Appendix 1.

Business Case and agreements

As part of the required business case and NHS internal process to move the scheme forwards and secured the funding outlined above, detail costings on the fit out and delivery of the scheme are now required. This requires the appointment of an architect and to progress the next stage of design works for the fit out of the commercial space.

The intention is for the Council to appoint a preferred architect firm from the NHS Shared Business services Framework with specialist NHS design experience to carry out the necessary RIBA stage 3 design works with fees to undertake this element being capped at Fig. B in Exempt Appendix 1. This work to be completed by the 31/10/2026 and will form the basis of the NHS business case approval.

If RIBA stage 4 works are required, additional design fees will need to be paid to the architect of up to the value of Fig. C of Appendix 1, MBC will be indemnified for all fees by the NHS with the relevant Memorandum of Understanding in place to secure this.

Programme

The healthcare proposal has advanced considerably over the past twelve months:

•  NHS Strategic Outline Case received initial support in January 2026.

•  NHS capital funding identified to support delivery of the facility.

•  Memorandum of Understanding agreed in principle between the parties summer 2026.

•  Section 2 Heads of Terms issued by NHS in September 2026

•  Further design and technical work to be appointed and completed by 31/10/2026 to support the NHS Full Business Case and procurement approvals.

Finance

The financial returns meet the council’s current hurdle rates and the proposed third-party funding provision which assist in the delivery of the project on these terms.

Any necessary procurement exercises for commissioning consultancy advice to ensure MBC standards are met by the Architect will be conducted in accordance with financial procedure and procurement rules.

Overall, for finance there will be a positive effect, as the already identified investment in the capital programme will produce a rate of return.

Social Value

The proposal will deliver significant social value through the provision of a new integrated healthcare facility within Maidstone town centre, improving access to primary care, community healthcare, mental health and wellbeing services for both existing and future residents. The facility will support the Council's wider regeneration aspirations for Maidstone East whilst meeting the healthcare needs arising from population growth across the borough.

The recommendations contained within this report would be delivered using existing Council resources, supported where required by specialist legal, property and technical advisers to progress the funding, lease and healthcare delivery arrangements.

The NHS capital investment will significantly improve the financial viability of the wider Maidstone East development, helping facilitate the delivery of 180 new homes, including affordable housing, alongside supporting infrastructure and public realm improvements. The proposal will therefore contribute towards both improved health outcomes and the provision of much-needed housing within the borough.

The proposal will have a positive social impact through the delivery of a major community healthcare asset, increased housing delivery, improved accessibility to health services and the attraction of substantial external investment into Maidstone East, supporting the long-term regeneration of the town centre.

ENVIRONMENT

The proposed healthcare facility will form part of the wider Maidstone East regeneration scheme, delivering modern, energy-efficient accommodation constructed in accordance with current building regulations and sustainability standards. The development will support the Council's wider environmental objectives by bringing forward a high-quality mixed-use development within a sustainable town centre location.

Special attention is needed regarding the implications of the following to action of the Biodiversity and Climate Change Action plan:

•  Action 9.3 - Deliver Policy that ensures sustainability criteria is used for all Maidstone Borough Council construction of new buildings (offices, housing, leisure facilities) and sustainability criteria is part of decision-making process for all Maidstone Borough Council building acquisitions, to ensure buildings owned by the council are sustainable, future proofed, and align with our net zero commitment.

•  Action 9.4 - Establish criteria for investment in climate change and biodiversity and invest to save schemes (e.g. renewables, heat networks). These will consider relative impact in terms of carbon reduction and ease of delivery, such that expenditure is focused on deliverable, affordable initiatives that maximise impact on the carbon reduction targets.

The occupation of the commercial accommodation by NHS healthcare providers will promote the efficient use of a sustainable town centre location, with excellent access to public transport, walking and cycling routes. The co-location of healthcare services within a single facility will reduce the need for residents to travel between multiple sites and support more sustainable patterns of movement across the borough.

Whilst all development activity has an associated carbon cost, the overall environmental impact of the proposal is considered positive. The recommendations support the regeneration of a brownfield site, the delivery of modern and energy-efficient accommodation, improved access to local healthcare services and the creation of sustainable communities in accordance with the Council's adopted strategies.

Overall whilst any development has a carbon cost, the overall impact is positive as the homes provided will have improved standards and contribute to the council’s Biodiversity and Climate Change action plan targets.

The recommendations align with and contribute towards the Council's Climate Change Strategy and Biodiversity Strategy 2025-2030 through:

•  Supporting sustainable town centre regeneration.

•  Encouraging active and sustainable travel choices.

•  Delivering environmental and biodiversity enhancements.

•  Promoting efficient use of previously developed land.

•  Supporting high-quality development that is adaptable to future climate challenges.

Nature recovery – The site will deliver at least 80% BNG gain for the local area through onsite improvements.

Climate resilience - the recommendations align with the Council’s strategic aims by supporting a high-quality place adapted for a changing climate, and by enabling practical improvements to the environmental performance of accommodation used to meet housing need.

Supporting the delivery of the Corporate priorities of:

•  Create a fairer economy for people and planet

•  A high-quality place adapted for a changing climate

The delivery of the Health care facility and receipt of third-party monies will produce a positive financial outcome through maintaining the required level of return, as well as partially de risking the financial commitment from MBC, whilst also helping deliver good quality affordable homes, and public realm provisions.

High environmental standards for public space, new homes and commercial accommodation will be achieved as part of the development and contribute to the Councils Biodiversity and Climate Change Action Plan. Therefore, the overall balance of Finance, Social and Environment is a net positive if the recommended option is agreed.

The matter was considered and supported by the Housing Policy Advisory Committee at its meeting on 13 October 2026.

Alternative options considered

The alternative option was to not approve the proposed lease arrangement and funding sources. The Council would lose an excellent opportunity to secure a leading healthcare facility at the centre of the regeneration project and secure third-party funds which improves the overall viability of the project.

The Cabinet did not choose this option for several reasons, including the significant amount of work and negotiation that has been completed by officers and the significant viability benefits by securing substantial third-party capital investment into the redevelopment of the Former Royal Mail Sorting office site, by reducing the Councils commercial and financial cost associated with delivering and letting the commercial accommodation.

The option chosen provides the delivery of a major new healthcare facility within Maidstone town centre whilst providing improved access to primary, community and neighbourhood healthcare services for existing and future residents.

Supporting Documents

Agreement to Lease Commercial Space -Maidstone East.pdf

Details

ReferenceCall-ins0
OutcomeRecommendations Approved
Decision date21 Oct 2026
Effective from31 Oct 2026
Expected date21 Oct 2026
Originally due21 Oct 2026
Lead officerPhilip Morris
Subject to call-inYes