Maidstone Borough New Local Plan – Scoping Consultation (Regulation 20) Document

November 18, 2026 Cabinet (Cabinet collective) Key decision In call-in window View on council website
Full council record

Purpose

To seek approval to publish the Maidstone Borough New Lock Plan Scoping Consultation (Regulation 20) document (Appendix 1) for public consultation from 4 December 2026 to 10 January 2027. The timeframe is longer than the minimum 4-weeks notice as has been the standard consultation period for other local planning authorities at this stage, to account for the consultation taking place over the Christmas holidays.

This will be the first consultation on the New Local Plan and the first under the Town and Country Planning (Local Planning) (England) Regulations 2026. The document is early stage and high-level, seeking views on the Plan’s scope and content, the evidence needed, the borough’s key priorities and emerging vision, and how people wish to be engaged.

Approval is also sought to publish the Plan Timetable, the Notice of Intention to Commence plan-making and supporting documents, alongside granting delegated authority for the Head of Planning and Economic Development to sign off the Strategic Environmental Assessment (SEA) Scoping Report for consultation with the three statutory bodies, when it is ready.

Decision

 That:

  1. The content of the Plan Timetable (Appendix 3) and formal Notice of Intention to Commence (Appendix 5) be noted and agreed for publication in line with the Town and Country Planning (Local Planning) (England) Regulations 2026;
  2. The Maidstone Borough New Local Plan Scoping Consultation (Regulation 20) document (Appendix 1) be approved for formal public consultation from 4 December 2026 until 10 January 2027;
  3. The content of the summary Project Initiation Document (PID) (Appendix 2), Baseline Evidence Report (Appendix 4), Readiness Tracker (Appendix 6), the Scoping Consultation Summary document (Appendix 7), and the Infrastructure Position Statement (Appendix 8) be noted and agreed for publication as supporting documents alongside the Maidstone Borough New Local Plan Scoping Consultation (Regulation 20) document (Appendix 1);
  4. The Council continue to engage with infrastructure providers, especially water companies, as the New Local Plan progresses in order to plan for development appropriately in line with national planning policy and relevant legislation;
  5. The Head of Planning and Economic Development be given delegated authority to sign off the Strategic Environmental Assessment (SEA) Scoping Report for formal four-week consultation with the three statutory bodies (Environment Agency, Historic England and Natural England) in accordance with the Environmental Assessment of Plans and Programmes Regulations 2004 (SI 2004/1633); and
  6. The Head of Planning and Economic Development be given delegated authority to make editorial changes to the Scoping Consultation and/or associated documents, as necessary, prior to public consultation.

Reasons for the decision

The New Local Plan is arguably one of the Council’s most important tools for shaping how Maidstone develops and changes. When planned well and supported by the right infrastructure, development can create lasting social, environmental and economic value: revitalising neighbourhoods and centres, providing homes and good jobs, improving services and connections, supporting healthier and more inclusive communities, strengthening local prosperity and helping to create climate resilience, nature recovery and environmental enhancement.

Whilst the Council is bound by the somewhat prescriptive nature of the national planning system, including the Town and Country Planning (Local Planning) (England) Regulations 2026, the National Planning Policy Framework (NPPF, August 2026) and Planning Practice Guidance, and the ‘Create and Update a Local Plan (CULP) guidance’; the intention of this New Local Plan is to be as locally specific as possible and to deliver meaningful positive outcomes for the people of Maidstone borough. The New Local Plan will influence not only where homes, jobs and infrastructure are provided, but also the quality, character and connections of the places in which people live, work, learn and spend time. For Maidstone Borough, good plan-making is therefore about securing a fairer distribution of opportunities and benefits, including for communities experiencing disadvantage, and leaving a positive legacy for current and future generations. Once the New Local Plan is adopted, it will replace the current Local Plan Review 2021-2038.

Content of the Scoping Consultation (Regulation 20) document

The content expected within a scoping consultation document is clearly set out in the national ‘Create or Update a Local Plan (CULP)’ guidance1. From a technical perspective, the proposed Scoping Consultation document is an early stage, high-level document broadly seeking: input on the proposed scope and content of the plan; views on how people, bodies and organisations wish to be engaged in the plan-making process; feedback on the proposed evidence base needed; as well as feedback on the borough’s key priorities and what should be considered for the Plan’s future Vision and Objectives. At this early scoping stage, there are no proposed spatial options, no policies and no sites identified in the Plan. These will come at a later stage, once the scope and content of the Plan has been established through this scoping exercise, alongside evidence gathering and wider stakeholder engagement.

The document itself is fairly short, at around 55 pages, and is split into three main sections: 1) Introduction – providing context and setting out headline facts about the borough, a resultant ‘SWOT analysis’ and set of eight key priorities, as well as setting the context for the Vision; 2) Scoping – setting out proposed plan content and likely evidence needed; and 3) Engagement Strategy – setting out proposed engagement principles and methods. There are 16 questions within the document – all with free text response options to allow maximum engagement, views and feedback at this early scoping stage.

The New Local Plan also provides a real opportunity to promote healthy lifestyles and reduce health inequalities. Weaved throughout the Plan from the outset is a health in all policies approach. Health and wellbeing is to be treated as a cross-cutting outcome of the choices we make throughout the plan-making process. Effects of the plan on physical health, mental wellbeing and health inequalities will be regularly considered and assessed through an iterative Health Impact Assessment that will be updated as the Plan progresses. This will be undertaken alongside a similarly iterative Equalities Impact Assessment.

Evidence base

Officers have worked with Procurement to appoint 10 separate consultancy firms across a range of specialist areas to produce a detailed technical evidence base to underpin the New Local Plan. This ranges from discrete topic areas such as a Strategic Housing Market Assessment, to plan-wide evidence such as a whole plan Viability Assessment. On the latter, demonstration of the viability and deliverability of policies and sites in the plan will be critical given the wider national and global macroeconomic uncertainties and current costs of development. All of this evidence in combination will help to ensure a robust, credible, evidence-led plan capable of being found ‘sound’ at examination. In addition to the initial procurement exercise, work is now being finalised to ensure a full suite of evidence is commissioned, for example the Gypsy and Traveller Accommodation Needs Assessment and Sports and Playing Pitch Strategies.

Other documents

Scoping consultation (Regulation 20) summary document: This is a slimmed-down, plain-English summary version of the full length Scoping Consultation document. It includes the key plan making stages, the proposed key priorities for the borough and proposed engagement methods and principles. It also includes all 16 consultation questions.

Project Initiation Document (PID) summary: The Project Initiation Document (PID) is a practical management tool designed to support the successful delivery of the New Local Plan. It helps to define and communicate the plan’s scope, governance, evidence and resource needs, and engagement approach while ensuring readiness for each stage of plan-making. It is a requirement to produce a PID in the early ‘get ready’ stages under the national Create or Update a Local Plan (CULP) guidance2. There is not a requirement to publish the PID. However, officers recommend that a summary PID (with any sensitive information removed) is published for maximum transparency in the process. The summary PID outlines the governance arrangements which include the cross-party Local Plan Member Steering Group, which has been consulted on the PID and associated summary PID. The robust governance arrangements and detailed evidence and resource needs will ensure we have a sufficient project management framework in place to commence plan making.

Plan Timetable: This is also required under the CULP guidance. As a council, we must create, publish and keep the plan timetable up to date. What the Plan timetable must include and how we have met the requirement is set out below:

•  the matters the plan will deal with – the plan will establish how policies will be used and developed, setting out priorities for housing, employment, infrastructure, design and environmental standards;

•  the geographical area that the plan will cover – Maidstone Borough Council administrative area;

•  any supplementary plans that will be prepared – no supplementary plans are to be produced;

•  and key milestone dates- see below

To meet the timetable requirements, we must publish both a plan dataset and plan timetable dataset, following the approved data standard. The local plan housing requirement is part of the plan dataset.

Baseline Evidence Report: An important task in the ‘get ready’ stages of plan making is ‘baselining’. This involves gathering data and information, and carrying out analysis to inform and contribute to: shaping the direction of plan-making; drafting a vision; scoping and preparing evidence base; and scoping for the Strategic Environmental Assessment5. It also helps meet the ‘survey of the area’ requirement set out in section 13 of the Planning and Compulsory Purchase Act 2004.

The baseline evidence report seeks to show the current picture of the area as well as touching on the potential future picture of the area. Data sources include existing monitoring of the adopted Local Plan Review, ONS data, central government’s connectivity tool and Defra datasets. The baseline evidence report shows that Maidstone Borough is a place of growth and opportunity – with a rising population, new housing and jobs, and a central role in Kent’s economy. The challenge will be to direct future development in a way that addresses the priorities of housing affordability, transport and connectivity improvements, climate action, and biodiversity conservation.

Whilst it is not a requirement to publish this report, officers recommend publication to show clearly how the baseline evidence gathering has helped to inform the borough’s SWOT analysis and key priorities as presented in the Scoping Consultation (Regulation 20) document.

Notice of Intention to Commence: This is a formal requirement for the Council to produce. It is a procedural notice akin to a Public Notice and must be published on the Council’s website. It sets out the Council’s formal intention to commence plan-making under the new planning system, adhering to the CULP guidelines.

Whilst the CULP guidelines require a Local Planning Authority to give a minimum of 4-months’ notice of intention to commence, officers have proposed a 6-month notice period. This would mean the official 30-month plan-making process starting in May 2027. Officers consider this to be an appropriate length of time to ensure as much baseline evidence as possible is available to give the best possible chance of producing a sound plan within 30-months. Rushing to complete necessary get-ready tasks and early stakeholder engagement within 4-months runs the risk of being underprepared to draft a suitably evidenced, robust and sound plan within the prescribed timeframe.

Readiness Tracker: This is a standardised template document produced by the Government, containing a series of actions that are categorised as either red, amber or green. At this current stage, it is not expected that all actions will be ‘green’. The purpose of the tracker is primarily as an internal project management tool aimed at ensuring the local planning authority have undertaken all the necessary steps to be ready for the ‘Gateway 1’ self assessment.

The tracker is looking at progress in the following areas:

•  Preparing and publishing a local plan timetable

•  Establishing project management and governance

•  Consulting and engaging on the plan

•  Scoping the anticipated content of the plan

•  Progressing the Strategic Environmental Assessment (SEA)

Since the October 2026 meetings the following changes highlighted in the table below have occurred.

Infrastructure Position Statement: A high-level consultation with infrastructure providers was undertaken over the summer of 2026 to understand the whole system capacity within the Borough (details to be located in appendix 8). A summary of the findings is highlighted in appendix 8. The next steps are to re-engage with infrastructure providers using the information obtained from the recent call for sites exercise to ascertain if any of the proposed growth locations would present a problem and therefore help to steer the spatial strategy.

Water supply has been a particularly prominent issue in the Borough. Within most of Maidstone Borough, Soth East Water (SEW) are responsible for water supply only. Waste water (sewage) is the responsibility of Southern Water for the Borough. Please note that SEW does not however supply the area to the north of the borough; including: Bredhurst, Kemsley Street, Lidsing, Beechy Wood, Round Wood, Malling Wood, Tunbury Wood or Coal Bottom, this is supplied by Southern Water.

There are statutory duties on water companies under S37 of the Water Industry Act 1991, water companies have a duty to “maintain, improve, and extend” their water supply networks to account for future water needs. Additionally, water companies are required to undertake long-term resource planning.

During the preparation of the Local Plan Review 2021-2038, the Council consulted South East Water to ensure that the water infrastructure aligned with the anticipated housing and commercial development. South East Water raised no concerns about the Local Plan Review 2021-2038, which set out the housing need for the Borough was 1,157 new homes per annum.

The Council’s Local Plan Review 2021 - 2038 was adopted on 20 March 2024. Subsequent to the Local Plan Review’s adoption, South East Water have highlighted issues in March 2026 due to the inconsistencies between their own planned growth set out in their Water Resources Management Plan and the Local Plan Review 2021-2038 housing trajectory. However, upon further discussions in the spring and summer 2026 it would appear that in the short term there is capacity in the system to meet the borough’s forecast new housing development coming forward until a new WRMP comes forward in 2029.

Engagement with SEW will continue, with a focus on the new information provided by the recent Call for Sites exercise, as set out above. This will help ensure that the Council is providing SEW every opportunity to feed into the New Local Plan process.

SEA Scoping Report: A Strategic Environmental Assessment (SEA) must be undertaken when preparing a Local Plan. The assessment process is iterative and helps inform and shape the content of the plan by assessing it’s potential impacts on the environment and how these may be avoided, reduced or mitigated. The SEA Scoping Report must be sent to the three statutory bodies (Natural England, Historic England and the Environment Agency) as part of a five-week consultation. The Scoping is a technical, specialist statement and does not set any scoring or assessment at this stage. It sets out the framework in which the scoring and assessment will take place at the later stage of the full SEA. The report defines the key environmental issues that the Local Plan should address and the framework for assessing likely environmental effects. It includes a description of the current environmental conditions and trends across the plan area such as:

•  Biodiversity, flora and fauna

•  Soil and agricultural land.

•  Water resources and flooding.

•  Air quality.

•  Climatic factors and carbon emissions.

•  Cultural heritage and archaeology.

•  Landscape and townscape.

It also identifies the main environmental challenges facing the area. The Scoping will include a set of sustainability objectives, assessment questions, indicators and monitoring measures that will be applied in the full SEA. It is not subject to wider public consultation. The SEA Scoping consultation with these bodies is therefore distinct from the Regulation 20 Local Plan scoping consultation.

The SEA Scoping Report is currently being produced by specialist consultants, it is anticipated that it may be drafted in time for the December consultation on the New Local Plan Scoping Consultation document. As such, Members are asked as part of the report recommendations, to agree delegated authority to the Head of Planning and Economic Development, to sign off the SEA Scoping Report when it is drafted for the necessary five week consultation period with the three statutory bodies.

Summary

In summary, a great deal of work has been undertaken in this early ‘get ready’ stage of plan preparation. As a local planning authority, we are now in a good position to publish our official notice of intention to commence plan making, which starts the formal process. Alongside this, we shall formally publish our Local Plan Timetable, which sets out the stages and expected timing of the New Local Plan preparation.

The first opportunity for public engagement in helping shape the New Local Plan is the proposed Regulation 20 Scoping Consultation – as set out in this report. This is the high-level scoping of what the plan should contain, what they key priorities might be for Maidstone borough, and asks people how they wish to be involved in and engaged with the plan-making process as it progresses. At this stage there are no proposed spatial options, no policies and no sites to comment on.

Policy Advisory Committee Feedback

The matter was considered and supported by the Planning and Communities Policy Advisory Committee at its meeting held on 10 November 2026.

Alternative options considered

‘Do Nothing’ – This would mean that the Council does not undertake a public consultation on the Maidstone Borough New Local Plan Scoping Consultation (Regulation 20) document.  The Council is currently unable to demonstrate a five-year housing land supply and one of the key ways for the authority to address this is through the preparation of a New Local Plan.

The Cabinet did not choose this option, as any delays to the New Local Plan preparation timetable, which had been changed to a 30 month plan timetable, may result in the Council being unable to sufficiently progress the New Local Plan prior to Unitarisation. Additionally, the New Local Plan Scoping Consultation (Regulation 20) document has been prepared by officers with wider input from the Corporate Leadership Team, the Local Plan Member Steering Group and the Cabinet Member for Planning Policy and Management. It has also been informed by the more general discussions on the New Local Plan at the October PAC meeting and Overview and Scrutiny Committee.

The Council is required to review and update a Local Plan every five years, of which the Council will be three years in, by March 2027. Failure to do so would mean the Council risks failing in its statutory duty under the Planning and Compulsory Purchase Act 2004. 

Supporting Documents

Appendix 7 Maidstone Borough New Local Plan Scoping Consultation Regulation 20 Summary document.pdf
Appendix 4 Baseline Evidence Report.pdf
Appendix 8 Maidstone Borough Council Infrastructure Position Statement Stage 1 Infrastructure Capa.pdf
Appendix 2 Summary Project Initiation Document PID.pdf
Maidstone Borough New Local Plan Update.pdf
Appendix 1 Maidstone Borough New Local Plan Scoping Consultation Regulation 20 document.pdf
Appendix 3 New Local Plan Timetable.pdf
Appendix 5 Notice of Intention to Commence.pdf

Details

Reference0
OutcomeRecommendations Approved (subject to call-in)
Decision date18 Nov 2026
Expected date18 Nov 2026
Originally due18 Nov 2026
Plan published4 Nov 2026
Lead officerTom Gilbert, Mark Egerton, Helen Smith
Subject to call-inYes