Town Centre Vision and Deliberative Engagement Programme (formerly Town Centre Strategy)
November 18, 2026 Cabinet (Cabinet collective) Key decision In call-in window View on council websiteFull council record
Purpose
To seek approval for the Maidstone Town Centre Vision, which has been prepared following extensive research and engagement including the town centre deliberation with residents of the town centre. The vision will serve as the Council’s long-term statement of ambition for Maidstone town centre to 2050. There is also an 18-month action plan of projects to deliver recommendations from the residents’ deliberation.
Decision
That:
- The Town Centre Vision to 2050 be approved;
- The Chief Executive be granted delegated authority to make minor, typographical and inconsequential changes to the Town Centre Vision to 2050 document to prepare it for publication;
- The findings of the town centre deliberation be noted; and
- The action plan of projects to be delivered in the next 18 months be approved, as a launchpad to further development of resources to fully deliver the Vision and include an indicative timetable of the next stages.
Reasons for the decision
Maidstone Town Centre has a diverse and changing population with significant movement into and out of the area; it is younger and more ethnically and linguistically diverse than the borough overall. Home to almost 20,000 residents, the area contains some of the borough's most disadvantaged neighbourhoods, with 40% of its Lower Super Output Areas1 falling within the 20% most deprived areas nationally overall. Crime is the most significant and widespread issue, with 60% of town centre LSOAs ranking within the 20% most deprived nationally for crime. The data also highlights challenges relating to housing affordability, child poverty, employment, skills and environmental quality. While access to services is generally good, many residents experience social and economic disadvantage including high housing costs and financial insecurity which can limit opportunities and contribute to poorer life outcomes. Addressing these interconnected challenges will require coordinated action to reduce inequalities and improve quality of life across the town centre. A map showing the relevant LSOA’s is below:
Maidstone Town Centre is the borough’s main centre for jobs and business. It has a much higher concentration of jobs than elsewhere in the borough. The concentration of full-time jobs is almost three times the borough average, while part-time jobs are more than three-and-a-half times as concentrated.
The Town Centre also has a slightly higher concentration of VAT-registered businesses than the borough overall and is characterised by a strong service sector economy. Retail businesses account for around 16.5% of all registered business units in the Town Centre, compared with 7.8% borough-wide, whilst accommodation and food services represent 10.6% compared with 5.2% across the borough. Finance and insurance, arts, entertainment and recreation, and transport-related businesses are also more prevalent also. The Town Centre additionally supports a greater proportion of larger employers, underlining its role as a key employment location.
Footfall data reinforces the Town Centre's importance as a destination for shopping, work, leisure and services. Annual footfall increased from 21.6 million visits in 2023/24 to 25.1 million visits in 2024/25, representing growth of 15.9%. However, footfall fell to 22.3 million visits in 2025/26, an 11% reduction on the previous year. Despite this decline, visitor numbers remain substantial and continue to support the Town Centre's retail and hospitality businesses. Retail vacancy rates remain relatively low when compared with many town centres nationally, increasing only slightly from 9.9% in 2025 to 10.5% in 2026. While this suggests that the majority of retail units remain occupied and active, the increase, alongside declining footfall, may indicate emerging pressures within the retail market.
Together, these indicators suggest that Maidstone Town Centre remains economically resilient but faces challenges common to many town centres, including changing consumer behaviour, online retail competition and wider economic uncertainty. The Town Centre boundary set out by the Local Plan Policy LPRSP1, can be seen below:
Over recent years, and with support across political parties, the Council has undertaken a substantial programme of work to better understand Maidstone town centre, shape its future direction and deliver improvements for residents, businesses and visitors. A summary of recent projects and interventions, which reflect the needs and aspirations identified in this work, are available at Appendix 1. It has also informed the Vision statement at Appendix 2.
Development of a Town Centre Picture
Work to understand Maidstone Town Centre as a place has considered its role as the County Town of Kent and the borough’s principal centre for retail, employment, services, leisure and civic life and its rich heritage. It has also explored the area’s particular challenges, alongside those facing town centres nationally, including:
• Changes in retailing and the growth of online shopping.
• The impacts of Covid-19.
• Traffic congestion, pollution and poor pedestrian permeability.
• Areas of the town centre that feel fragmented or neglected.
• The need to improve sustainability and climate resilience.
A substantial body of work has been brought together to build a clear picture of the town centre, its strengths, opportunities and challenges. This includes consideration of its heritage, riverside setting, parks, transport connections, and growing residential population. Existing initiatives and projects across the town centre were also reviewed and comprehensive engagement with councillors has helped to shape this important document.
This has been supplemented by public engagement and town centre work undertaken since 2022, including research and evidence relating to the public realm, transport, heritage, lighting and infrastructure. Further engagement in summer 2026 provided residents and stakeholders with opportunities to share their experiences and views on the future of the town centre. Comprehensive engagement with councillors has added further insight. Together, this work provides a strong evidence base for understanding the town centre today and the opportunities and priorities for its future.
A Vision for Maidstone Town Centre
The new Maidstone Town Centre Vision document, attached at Appendix 2, provides a corporate strategic vision for Maidstone Town Centre to 2050. It is not a detailed delivery plan, but a high-level framework that establishes a long-term direction for the town centre. It is a place-based strategic vision providing a clear direction for Maidstone Town Centre.
The document is intended to guide the future of the town centre through to 2050, providing a framework for spatial planning, investment decisions and regeneration activity. This emphasises partnership working, supports the development of appropriate planning policy, helps to attract investment, promotes and celebrates the town and provides a basis for monitoring progress. All of this combined will help to:
• Bring partners together around a common ambition;
• Inform future planning policy;
• Align investment strategies and delivery activity;
• Attract and guide new investment;
• Support and empower local involvement;
• Promote and celebrate the town centre; and
• Measure progress over time.
The Vision document sets objectives and priority actions designed to improve the quality of life of people living in the town centre, supporting stronger communities, addressing local challenges, and ensuring that the benefits of future investment and change are shared by town centre residents.
The overarching vision sets out the ambition for Maidstone Town Centre to 2050: a welcoming, inclusive, vibrant, and prosperous place that is sustainable and well connected. It celebrates what makes Maidstone distinctive, particularly its rich heritage and riverside setting, while creating a town centre where people want to live, work, visit and spend time.
Sat beneath the vision, there are four missions which provide the framework for future decisions and actions. Implementation of the Maidstone Town Centre Vision document will involve partnership working, alignment of existing strategies/actions, future planning policy, attracting investment, community involvement and monitoring through a Council-led governance structure.
The Four Missions and their key messages are set out in more detail below:
Pride in Our Town as a Good Place to Live - The aim is to create a town centre people feel proud of and want to spend time in with the following key priorities:
• Improve public spaces and the appearance of the town centre.
• Foster stronger communities and civic pride.
• Create a cleaner, greener and safer environment.
• Encourage more people to live in the town centre through high quality housing.
• Celebrate and restore heritage assets.
• Improve health and wellbeing through walking, cycling and community activities.
• Empower residents to influence future change.
A Sustainable Economy - The aim is to develop a prosperous, resilient and diverse town centre economy with the following key priorities:
• Reduce reliance on traditional retail.
• Expand leisure, culture, arts, education and public services.
• Support local businesses and start-ups.
• Increase visitor numbers and tourism.
• Strengthen the evening economy.
• Encourage temporary and meanwhile uses of vacant premises.
• Attract public and private sector investment.
A Place that is Accessible to All - The aim is to make the town centre easy to reach and use for everyone with the following key priorities:
• Improve accessibility for people with disabilities.
• Enhance pedestrian, cycling and wheeling routes.
• Improve public transport accessibility.
• Reduce barriers created by roads and traffic.
• Improve connectivity to nearby parks and neighbourhoods.
• Increase access to the riverside.
• Improve digital accessibility and information.
A Healthy, Green and Sustainable Future - The aim is to create a climate-resilient, biodiverse and environmentally sustainable town centre with the following key priorities.
• Increase tree planting and green infrastructure.
• Improve parks, public spaces and biodiversity.
• Reduce pollution and encourage sustainable travel.
• Better manage water use and flood risk.
• Celebrate and improve access to rivers and waterways.
• Promote energy-efficient buildings and low-carbon development.
• Reuse existing buildings wherever possible.
Town Centre Deliberative Engagement
Following a competitive tender process, Urban Symbiotics were appointed to design and deliver the deliberative engagement alongside the town centre visioning exercise. The engagement focused on residents’ quality of life and experiences of the town centre, enabling a broad range of voices to shape future decisions and inform evidence-based recommendations.
Engagement ran from June to September 2026. First, residents were invited to complete a short survey on their quality of life and experience of the town centre. The survey received 497 responses and covered the best and most difficult things about living in or around the town centre, access to services, and areas of focus for the Council and its partners.
Results showed that while nearly half of respondents rated their quality of life positively (49.4%), over a quarter (26.7%) reported a poor or very poor quality of life, with disabled residents, carers, and older adults disproportionately affected. Participants described poor quality of life not as the result of a single issue, but as the cumulative effect of multiple pressures - including safety, housing, transport, and environmental neglect - combined with a lack of confidence that conditions will improve.
The survey was followed by three youth workshops, two stakeholder workshops, and a series of resident workshops involving individuals selected to reflect a diversity of backgrounds and lived experience. Participants established eight recurring themes that captured their priorities for the town centre:
• Safer, quieter and more welcoming streets;
• Cleaner, greener public realm;
• Better connected and easier to get around;
• Stronger community, belonging and places to meet;
• A more distinctive town centre, heritage and local economy;
• Clearer information, trust and local voice;
• Homes, HMOs and neighbourhood quality;
• Stronger support for vulnerable people.
A combined resident and stakeholder workshop followed, before sessions were held to finalise the emerging priorities and recommendations.
Participants debated trade-offs and key areas of focus, agreeing on the following key messages:
• Invest in projects that make the community feel better and more connected;
• The Council should invest its limited budget into actions where it can have a direct impact and that can be seen;
• Invest in young people;
• The Council needs to do more to communicate all the good work it does and to present a positive picture of Maidstone Town Centre;
• All projects should consider the impact on all age groups and have accessibility at the centre;
• A resident sounding-board process should be set up, and the sounding board should be engaged as part of shaping projects.
They also prioritised four new theme areas as shown in the diagram below:
Sitting beneath the four agreed themes are two overarching programmes:
• Build a community foundation for lasting change – bring together new and established communities and generations together to shape and sustain change beyond individual projects; strengthen existing community organisations; and establish ongoing ways for communities to influence decisions and see the impact of their contribution.
• Tell one shared story about Maidstone and develop its unique identity – define a shared identity for Maidstone; celebrate Maidstone’s people, diversity, heritage and character; establish a coordinated and accessible communications programme to show what is changing, how communities have influenced it, and how people can participate.
Three priority projects were also identified:
• Create a safe and supportive town - build on existing safety initiatives across the day, twilight and evening; address both safety and perceptions of safety, which stakeholders noted can affect town centre trade as well as residents' confidence to visit; intervene earlier at the underlying causes of antisocial behaviour; alongside support for vulnerable residents.
• Invest in young people and their futures - assess and progress options for diverse youth spaces and activities; create real pathways into skills and work; reach young people earlier including those at risk of disengagement; and involve them directly in shaping provision.
• Create more reasons to visit and spend time in Maidstone - strengthen events, pop-ups and cultural activity; celebrate existing and new communities; make greater use of the river, parks, heritage and public spaces; and bring Maidstone's heritage and character to life to give people reasons to visit, stay longer and return.
Their aspiration was for a town centre that is “Safe, Thriving and Celebrated”.
The full findings of the deliberation can be seen at Appendix 3. A full action plan has been developed in response to the priorities and recommendations arising from the deliberation, translating these into proposed projects.
Town Centre Action Plan
The Corporate Strategy Year Two Action Plan allocated £1m to improve quality of life for Town Centre residents. Given the socio-economic evidence which demonstrates significant challenges of financial insecurity for town centre communities, £100k was earmarked for additional welfare support, supplementing the existing provision delivered by the Health, Inclusion and Partnerships team including the Community Resilience Fund.
The remaining £900,000 is available for projects responding to the priorities and recommendations arising from the deliberation. It is proposed that the action plan period and funding runs to 31 March 2029 as we know Maidstone Borough Council will remain as a sovereign body until at least that date given that Local Government Reorganisation will be delayed for at least the period to 1st April 2029.
Officers identified potential projects across the two overarching programmes and three priority project areas. As the combined cost exceeded the available budget, officers and the Cabinet Member for Community Cohesion and Safety shortlisted the projects using the assessment criteria below:
Following shortlisting, projects with shared aims were merged or aligned to make the most effective use of available funding. A weighting exercise informed the proposed allocation of funding, seeking a balance across the three priority project areas. Smaller allocations were proposed for the two overarching programmes, which provide the foundations to support delivery across those areas. The proposed funding allocation is set out below:
The proposed action plan includes a wide range of projects responding directly to what residents told us through the town centre deliberation. The projects cover community involvement, safety and support, opportunities for young people, events and activities, and promoting the town centre and positive achievements.
There is deliberately a mix of projects, from practical interventions that people should see and experience in the town centre, through to projects intended to strengthen communities and involve residents in shaping what happens next. Examples include:
• Supporting voluntary and community organisations and creating ongoing opportunities for residents to influence change;
• Building on existing town centre safety activity, alongside work to tackle some of the underlying causes of people feeling unsafe;
• Creating more opportunities for young people, including youth activities and a Youth Hub providing employment, training and wider support;
• Supporting more events and activities to give people reasons to visit, stay longer and return to the town centre; and
• Better promotion of the town centre, including what is happening, what support is available and the progress being made.
The full action plan can be seen at Appendix 4.
Town Council
With the establishment of the new Maidstone Town Council, consideration will need to be given to how some elements of this work might be supported or sustained in the longer term. In particular, the emphasis within the deliberation on community involvement, local voice and creating ongoing opportunities for residents to influence change. It would be premature to determine which activities or responsibilities might transfer now, the Town Council need time to establish itself and the future arrangements for local government reorganisation continue to develop.
The immediate focus will therefore be on establishing dialogue and partnership working with the Town Council as it develops, including consideration of its role in future engagement and community involvement. Over time, this can include discussion about whether there are elements of the programme which the Town Council may be well placed to support, lead or take forward as part of longer-term successor arrangements. Any such arrangements would need to be considered at the appropriate time, taking account of capacity, funding, governance and the wider arrangements arising from local government reorganisation.
Risk
The Vision is deliberately long term and provides a strategic direction rather than a detailed delivery plan. There is therefore a risk that, without continued focus and alignment of future plans, investment and activity, the ambitions within the Vision are not fully realised. This will be managed by using the Vision to help guide future decisions and investment and by monitoring progress over time.
There are risks associated with delivering a range of projects of this breadth, particularly where individual projects will require further development and may involve working with partners and communities. These will be managed through the delivery of the action plan, with individual projects subject to appropriate project management, governance and monitoring arrangements.
There is also a risk that the action plan does not deliver the changes residents expect to see following the deliberation. The proposed action plan seeks to mitigate this by prioritising projects that respond strongly to the deliberation, can make a lasting and visible difference and support a number of the programme’s aims. Continued involvement of residents through the proposed sounding board will also provide an opportunity for communities to remain involved as projects develop.
Committee Feedback
The matter was considered and supported by the Planning and Communities Policy Advisory Committee at its meeting on 11 November 2026.
The Overview and Scrutiny Committee also considered the matter, and supported the decision made, making the below recommendations to the Cabinet.
RESOLVED to RECOMMEND to the CABINET: That
1. The Town Centre Vision to 2050 be approved;
2. The findings of the town centre deliberation be noted; and
3. The action plan of projects to be delivered in the next 18 months be approved as a launchpad to further development of resources to fully deliver the Vision and include an indicative timetable of the next stages.
Alternative options considered
Option 2 – Note the background information presented but request further information and/or recommended changes to either or both the vision document and action plan including asking officers to complete further work.
Option 3 – Note the background information presented but refuse to support either or both the vision document and action plan.
The Cabinet did not proceed with either of these options as considerable work has been undertaken to understand the challenges facing the town centre, and participants have committed their time to developing priorities and recommendations. Not progressing the vision or action plan could undermine confidence that this engagement will lead to visible change and delay investment of the £900,000 allocated to projects arising from the deliberation. The chosen option also represents a completion of both officer and cross-party member time to set out a clear vision and key priorities, providing a strategic direction for Maidstone Town Centre to 2050.
Supporting Documents
Details
| Reference | 0 |
| Outcome | Recommendations Approved (subject to call-in) |
| Decision date | 18 Nov 2026 |
| Expected date | 18 Nov 2026 |
| Originally due | 18 Nov 2026 |
| Plan published | 4 Nov 2026 |
| Lead officer | Alison Broom, Ellis Mallett |
| Subject to call-in | Yes |