Property Acquisition Update for Council House Building Programme

November 18, 2026 Cabinet (Cabinet collective) Key decision In call-in window View on council website
Full council record

Purpose

To seek approval for changes to a previously agreed proposal property acquisition, including a small alteration to the proposed mix of scheme, which has a positive impact and the disposal of a small area of land once the scheme is completed.

Decision

That:

  1. The updated financial returns for the proposed acquisition, as shown in Exempt Appendix 3, which supports the Housing Development and Regeneration Investment Plan and overall Development Strategy be approved;
  2. Delegated authority be given to the Director of Finance and Resources to:

a.  Negotiate terms for the purchase of the proposed acquisition for the sum as shown in Exempt Appendix 3;

b.  Procure and enter into all such deeds, agreements, contracts and documents which may be required to facilitate the purchase of the site, and the subsequent redevelopment works required to deliver the scheme referred to, including (but not limited to) any related appointments such as suitably qualified consultants and a Contractor; and

c.  Subject to satisfactory conclusion of all due diligence to negotiate and finalise and complete all legal formalities, deeds and agreements which may be required to facilitate the purchase. This includes the transfer /disposal of the areas of land and visitor bays as detailed in the report and shown in Exempt Appendix 4.

  1. The authority’s designated legal advisers, in consultation with the Director of Finances & Resources, be authorised to negotiate and complete the necessary contract documentation, deeds and agreements associated with the purchase and construction works on the terms as agreed;
  2. It be agreed, post completion of the procurement process, to appoint a contractor for the works cost detailed in the financial summary at Exempt Appendix 3. If in the event tenders for the works cost exceed the agreed sum by more than 5% of that sum, officers will return to the Cabinet to seek further approval prior to the development itself commencing. If in the event tenders for the works are higher than the agreed sum detailed in the financial summary but less than 5% then the decision to continue will be made in consultation with the portfolio Holder and Section 151 Officer as long as the Council’s internal hurdle rates are met.

Reasons for the decision

Since the property acquisition was approved on 23 July 2025, the proposals have progressed and a number of changes have arisen which require the matter to be brought back to Cabinet for consideration and approval. The changes include a small alteration to the proposed mix of schemes, which has a positive impact, and the disposal of a small area of land once the scheme is completed. The updated report being presented considers the proposal against the following standard risk headings:

•  Site location and ownership.

•  Town Planning Status.

•  Schedule of accommodation, tenure mix and parking ratio.

•  Land Transfer and Legal arrangement.

•  Housing Management.

•  Deal structure and revised viability.

•  Delivery programme.

•  Professional team.

FINANCE

The financial returns meet the council’s current hurdle rates which assist in the delivery of the project on these terms.

Any necessary procurement exercises for commissioning consultancy advice, or contractors to ensure MBC standards are met will be conducted in accordance with financial procedure and procurement rules. Overall, for finance there will be a positive effect, as the already identified investment in the capital programme will produce a rate of return.

SOCIAL VALUE

The council’s affordable housing aims to deliver affordable housing for Maidstone residents, whilst ensuring the Housing Revenue Account remains solvent. The decision made would be delivered using existing Council resources, supported where required by specialist legal, property and technical advisers to progress the funding, lease and healthcare delivery arrangements. 

Completing the schemes and providing more affordable housing will reduce health inequalities by bolstering supply and availability of good quality affordable housing.

ENVIRONMENT

Providing new affordable homes will have an impact on the Council’s carbon footprint and 2030 Net Zero commitment. Highly thermally efficient, low carbon heating, and climate adapted housing through the delivery of renewable energy, active travel, and biodiversity enhancements as part of the development strategy will ensure alignment with the Biodiversity and Climate Change Action Plan.

Special attention is needed regarding the implications of the following to actions within the Biodiversity and Climate Change Action plan:

Action 9.3 - Deliver Policy that ensures sustainability criteria is used for all Maidstone Borough Council construction of new buildings (offices, housing, leisure facilities) and sustainability criteria is part of decision-making process for all Maidstone Borough Council building acquisitions, to ensure buildings owned by the council are sustainable, future proofed, and align with our net zero commitment.

Action 9.4 - Establish criteria for investment in climate change and biodiversity and invest to save schemes (e.g. renewables, heat networks). These will consider relative impact in terms of carbon reduction and ease of delivery, such that expenditure is focused on deliverable, affordable initiatives that maximise impact on the carbon reduction targets.

The units will be built to Nationally Described Space Standards and comply with building for life requirement where possible.

The development will reflect the local vernacular as conditioned throughout the planning process and as the developer in Kent based MBC will be contributing to the circular economy within the local area.

Overall whilst any development has a carbon cost, the overall impact is neutral as the homes provided will have improved standards and contribute to the council’s Biodiversity and Climate Change action plan targets.

The decision made aligns with and contributes towards the Council’s Change Strategy and Biodiversity Strategy 2025-2030 through:

•  Decarbonisation – MBC Planning policy ensures new developments are compliant with future standards in terms of energy efficiency

•  Encouraging active and sustainable travel choices.

•  Delivering environmental and biodiversity enhancements.

•  Promoting efficient use of land.

•  Supporting high-quality development that is adaptable to future climate challenges.

Nature recovery – The site will deliver at least 20% BNG gain for the local area through onsite improvements.

Climate resilience - the recommendations align with the Council’s strategic aims by supporting a high-quality place adapted for a changing climate, and by enabling practical improvements to the environmental performance of accommodation used to meet housing need.

Policy Advisory Committee Feedback

The matter was considered and supported by the Housing Policy Advisory Committee at its meeting on 4 November 2026.

Alternative options considered

Option 2 - The Cabinet could have chosen not to approve the purchase of the proposed acquisition based on the updated scheme. The Council would, however, lose an excellent opportunity to purchase a site in a rural area and to add to its affordable housing stock.

The Cabinet did not choose this option, as the property acquisition will assist towards much needed local needs affordable accommodation in the Borough, within a rural location, and contribute towards the Council House Building Programme delivery target. 

Supporting Documents

Property Acquisition Update.pdf

Details

Reference0
OutcomeRecommendations Approved (subject to call-in)
Decision date18 Nov 2026
Expected date18 Nov 2026
Originally due18 Nov 2026
Plan published4 Nov 2026
Lead officerPhilip Morris
Subject to call-inYes