Compliance with Digital Waste Tracking legislation
September 21, 2026 Chief Executive Officer (Officer) Approved View on council websiteFull council record
Purpose
To procure software in order to ensure the Council is compliant with new legislation
Decision
Compliance with Digital Waste Tracking legislation
To contract, via direct award, with Weightron Bilanciai Ltd for the provision of new software to ensure compliance with new Digital Waste Tracking legislation at a cost of £6,544 per year for 1 year with a 1 year extension option, noting that the relevant Assistant Director has approved a contracts exemption form.
The Legal Services Manager be authorised to negotiate, finalise and complete all necessary legal agreements and other documents to give effect to the above.
Reasons for the decision
The UK’s Digital Waste Tracking Regulations 2026 require all permitted waste?receiving sites to record controlled waste movements digitally from October 2026 in England, Wales and Northern Ireland, and from January 2027 in Scotland. These rules create a single national digital system replacing paper?based tracking and introduce legal duties, enforcement powers, civil sanctions, and mandatory data submission requirements.
The Waste Transfer Station (WTS) at Hermitage Lane Depot is a permitted waste receiving site and therefore in scope and needs to comply with this new legislation.
Currently, customers deliver waste to the WTS, gross weight of arriving vehicles is calculated via a software solution connected to the on-site weighbridge. Tare weight of the vehicles is then measured on exit, the software then calculates a nett weight of waste material which reported to the relevant authorities.
The new regulations require more detail to be reported including the type of waste being delivered. Officers have worked with Procurement to identify the optimum solution to these new demands. The current contracted weighbridge software and maintenance supplier is able to offer additional software which will ensure a seamless and compliant process will be in place.
The new software will allow more accurate reporting of waste and recyclable material. This improves the efficiency and effectiveness of recycling services and hence, the initial additional capital cost of the software can be drawn from Extended Producer Responsibility funding.
Alternative options considered
· In order to allow authorities time to adjust to the new regulations, Defra offer a spreadsheet-based solution. This offer only remains in place until April 2027, after which the digital reporting methodology must be used to remain compliant. The temporary spreadsheet solution would bring a new and significant administrative burden on to officers and is therefore not recommended.
· The Council could procure a new supplier of weighbridge software and maintenance technology; however it is a limited market and the cost and inconvenience of changing to a new supplier outweighs any financial benefit.
Details
| Outcome | Recommendations Approved |
| Decision date | 21 Sep 2026 |